NESO TEC REGISTER · GREAT BRITAIN

Battery storage projects in the connection queue on the SSEN Transmission (north Scotland) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown11122.7 GW in total
In planning91scoping or awaiting consent
Consented or building16closest to connecting
Built4connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

111 projects · page 1 of 3
ProjectCapacityStageConnection siteFrom
Tealing Energy Park
Battery storage · Onpath Energy Limited
1.4 GWScoping Tealing 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Spittal BESS Station
Battery storage · Igp Energy Storage 5 Limited
1.0 GWScoping Spittal 2 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Fort Augustus Storage
Battery storage · Glendoe Storage Limited
900 MWScoping Loch Nan Eun 275/18kV
SSEN Transmission (north Scotland)
Oct 2029
LGB300
Battery storage · LG-B-300
600 MWScoping LGB300 400KV Substation
SSEN Transmission (north Scotland)
Jul 2031
Akku Tealing Battery Storage
Battery storage · Akku Tealing Limited
500 MWScoping Tealing 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Alcemi Score 2 Battery Energy Storage Facility
Battery storage · Alcemi Storage Developments 5 Limited
500 MWScoping Alcemi Score Battery 400kV Substation
SSEN Transmission (north Scotland)
Mar 2031
Alcemi Score Battery Energy Storage Facility
Battery storage · Alcemi Storage Developments 5 Limited
500 MWScoping Alcemi Score Battery Energy Storage Facility 400Kv Substation
SSEN Transmission (north Scotland)
Mar 2031
Alyth BESS Station
Battery storage · Igp International Prospecting Limited
500 MWScoping Alyth BESS Station 400Kv Substation
SSEN Transmission (north Scotland)
Oct 2033
Brae House Farm
Battery storage · Qair Renewables UK Limited
500 MWScoping DOUNREAY 2 275 kV SUBSTATION
SSEN Transmission (north Scotland)
Jul 2032
Brigton of Ruthven BESS
Battery storage · Morris Leslie Limited
500 MWScoping Alyth 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Mybster 2 Battery Storage
Battery storage · Potencia Energy (Mybster) Ltd
500 MWScoping Thurso South 400kV Substation
SSEN Transmission (north Scotland)
Oct 2034
NatPower Kintore2 Green Energy Park
Battery storage · Np Spv 41 Limited
500 MWScoping Natpower Kintore 2 Green Energy Park 275Kv Substation
SSEN Transmission (north Scotland)
Oct 2033
New Deer Battery Storage
Battery storage · New Deer Energy Centre Limited
500 MWScoping New Deer 2 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
New Deer BESS Station
Battery storage · Abbotshaugh Energy Storage Limited
500 MWScoping New Deer 2 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Peterhead Battery
Battery storage · Peterhead Flexpower Ltd
500 MWScoping Peterhead 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Rothienorman Battery
Battery storage · Blackford Renewables Ltd
500 MWScoping Rothienorman 400kV Substation
SSEN Transmission (north Scotland)
Jul 2029
South Powrie Farm
Battery storage · Qair Renewables UK Limited
500 MWScoping Tealing 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Caithness Energy Storage
Battery storage · Baywa R.e. UK Limited
456 MWScoping Caithness Energy Storage 400Kv Substation
SSEN Transmission (north Scotland)
Oct 2034
Coachford 400MW BESS
Battery storage · Field Woodhead Ltd
400 MWScoping Coachford 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Field Kinardochy BESS
Battery storage · Field Kinardochy Ltd
400 MWScoping Kinardochy Substation 400/275kV
SSEN Transmission (north Scotland)
Oct 2035
Keith BESS Station
Battery storage · Ibv Coachford Energy Park Ltd
400 MWScoping Blackhillock substation
SSEN Transmission (north Scotland)
Oct 2033
Netherton BESS
Battery storage · Harmony Energy Limited
400 MWScoping Longside 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Blackhillock Battery
Battery storage · Blackhillock Flexpower Ltd
349 MWConsents Approved Blackhillock 400kV Substation
SSEN Transmission (north Scotland)
Oct 2028
Alcemi Midmill BESS
Battery storage · Alcemi Storage Developments 2 Limited
300 MWScoping Kintore 275kV
SSEN Transmission (north Scotland)
Dec 2029
Kynachan
Battery storage · Geocore Ltd
300 MWScoping Kynachan BESS 132kV Substation
SSEN Transmission (north Scotland)
Oct 2035
Spittal BESS
Battery storage · Field Spittal Ltd
300 MWScoping Spittal 132kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Stirling BESS
Battery storage · Anesco Limited
300 MWScoping Peterhead 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Zenobe Blackhillock 300 MW
Battery storage · Zenobe Blackhillock Limited
300 MWConsents Approved Blackhillock 275kV Substation
SSEN Transmission (north Scotland)
Apr 2026
MeyGen Tidal
Battery storage · Meygrid Limited
287 MWScoping Gills Bay GSP
SSEN Transmission (north Scotland)
Oct 2030
Stracathro BESS
Battery storage · Opdenergy UK 8 Limited
249 MWScoping Stracathro BESS 275kV Substation
SSEN Transmission (north Scotland)
Jun 2032
Whitehouse BESS station
Battery storage · Igp International Prospecting Limited
249 MWScoping Whitehouse 275kV Substation
SSEN Transmission (north Scotland)
Oct 2034
MeyGen Tidal
Battery storage · Meygrid Limited
237 MWConsents Approved Gills Bay GSP
SSEN Transmission (north Scotland)
Apr 2028
Achies BESS
Battery storage · Igp Energy Storage 5 Limited
200 MWScoping New Spittal 275kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Blairgowrie BESS
Battery storage · Woodside BESS Ltd
200 MWScoping Blairgowrie BESS 132kV Substation
SSEN Transmission (north Scotland)
May 2030
Broadford BESS
Battery storage · Field Devco Ltd
200 MWScoping Broadford 132kV Substation
SSEN Transmission (north Scotland)
Oct 2034
Corriemoillie BESS
Battery storage · Field Corriemoillie Ltd
200 MWScoping Corriemoillie 132kV Substation
SSEN Transmission (north Scotland)
Sep 2029
Dalchork Farm
Battery storage · Qair Renewables UK Limited
200 MWScoping Dalchork 132kV Substation
SSEN Transmission (north Scotland)
Oct 2032
Dounreay BESS
Battery storage · Field Devco Ltd
200 MWScoping New Dounreay 400kV substation
SSEN Transmission (north Scotland)
Oct 2034
Fort Augustus BESS
Battery storage · Field Devco Ltd
200 MWScoping Fort Augustus 400kV
SSEN Transmission (north Scotland)
Oct 2035
Fyrish Battery Storage
Battery storage · Field Fyrish Ltd
200 MWScoping Fyrish 132kV Substation
SSEN Transmission (north Scotland)
Oct 2029
Isenau Four
Battery storage · Isenau Energy Storage Resources Four Limited
200 MWScoping Corriemoillie 132/33kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Knocknagael BESS
Battery storage · Field Knocknagael Ltd
200 MWAwaiting Consents Knocknagael 132kV Substation
SSEN Transmission (north Scotland)
Jul 2029
L48 BESS Burnside
Battery storage · S4 UK DEV LTD
200 MWScoping New Deer 2 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Longside BESS
Battery storage · Baywa R.e. UK Limited
200 MWScoping Peterhead 2 400kV Busbar Extension
SSEN Transmission (north Scotland)
Oct 2033
Myreton BESS
Battery storage · GPC 1039 Ltd
200 MWScoping Tealing 132kV Substation
SSEN Transmission (north Scotland)
Oct 2028
Netherton Hub Bess
Battery storage · Field Netherton Ltd
200 MWScoping Longside 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
New Deer 2 BESS
Battery storage · Field New Deer Ltd
200 MWScoping New Deer 2 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Rigifa BESS
Battery storage · Field Rigifa Limited
200 MWScoping Gills Bay 132kV
SSEN Transmission (north Scotland)
Dec 2029
West Saval Battery Storage
Battery storage · West Saval Battery Storage Ltd
200 MWScoping West Saval Substation 132 kV
SSEN Transmission (north Scotland)
Oct 2030
Womblehill BESS Farm
Battery storage · RE Projects Development Limited
200 MWScoping Womblehill BESS Farm 132kV
SSEN Transmission (north Scotland)
Dec 2029
Page 1 of 3

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.