🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · SHET

Mybster 2 Battery Storage

Mybster 2 Battery Storage is a 500 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Thurso South 400kV Substation, with capacity due from October 2034. The connection agreement is held by Potencia Energy (Mybster) Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2034 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004479
Customer
Potencia Energy (Mybster) Ltd
Technology
Energy Storage System
Total capacity
500 MW
Change in this agreement
+500 MW
Capacity effective from
31 October 2034
Connection site
Thurso South 400kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Thurso South · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem