Home โ€บ Grid infrastructure โ€บ Connection queue

NESO TEC REGISTER ยท GREAT BRITAIN

Other projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown296.1 GW in total
In planning6scoping or awaiting consent
Consented or building12closest to connecting
Built11connected and operating

Map

Loading projectsโ€ฆ

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

29 projects
ProjectCapacityStageConnection siteFrom
Drax Power Station
Other ยท Drax Power Limited
3.9 GWBuilt Drax 400kV Substation
National Grid (England & Wales)
Lynemouth Power Station
Other ยท Lynemouth Power Limited
396 MWBuilt Blyth GSP
National Grid (England & Wales)
Tees Renewable Energy Plant
Other ยท Mgt Teesside Limited
285 MWBuilt Teeside Connection Node A 132kV Substation
National Grid (England & Wales)
Port of Mostyn
Other ยท Mostyn Seapower Limited
210 MWScoping Connah's Quay 400kV Substation
National Grid (England & Wales)
Jan 2032
Recell at Penrhos (BEGA)
Other ยท Recell Energy Bloom Developments Limited
210 MWConsents Approved Penrhos GSP
National Grid (England & Wales)
Oct 2027
Menter Mon Morlais Anglesey Marine Energy
Other ยท Menter Mรดn Morlais Limited
180 MWUnder Construction/Commissioning Penrhos GSP
National Grid (England & Wales)
Mar 2032
Recell at Penrhos (BEGA)
Other ยท Recell Energy Bloom Developments Limited
150 MWConsents Approved Penrhos GSP
National Grid (England & Wales)
Oct 2025
Port of Mostyn
Other ยท Mostyn Seapower Limited
140 MWScoping Connah's Quay 400kV Substation
National Grid (England & Wales)
Jun 2031
Menter Mon Morlais Anglesey Marine Energy
Other ยท Menter Mรดn Morlais Limited
100 MWUnder Construction/Commissioning Penrhos GSP
National Grid (England & Wales)
Mar 2030
Shbec
Other ยท Ttep Shb Ltd
83 MWConsents Approved South Humber Bank 400kV Substation
National Grid (England & Wales)
Jul 2029
Port of Mostyn
Other ยท Mostyn Seapower Limited
70 MWScoping Connah's Quay 400kV Substation
National Grid (England & Wales)
Dec 2030
Menter Mon Morlais Anglesey Marine Energy
Other ยท Menter Mรดn Morlais Limited
60 MWUnder Construction/Commissioning Penrhos GSP
National Grid (England & Wales)
Mar 2029
Indaver Rivenhall IWMF
Other ยท Indaver Rivenhall Limited
55 MWBuilt Braintree GSP
National Grid (England & Wales)
EMERGE Centre
Other ยท Uniper UK Limited
50 MWScoping Ratcliffe-On-Soar 132kV Substation
National Grid (England & Wales)
Jun 2029
Tilbury
Other ยท Tilbury Green Power Limited
43 MWBuilt Tilbury 132kV Substation
National Grid (England & Wales)
Thetford
Other ยท Epr Thetford Limited
41 MWBuilt Bramford 400kV Substation
National Grid (England & Wales)
Menter Mon Morlais Anglesey Marine Energy
Other ยท Menter Mรดn Morlais Limited
40 MWUnder Construction/Commissioning Penrhos GSP
National Grid (England & Wales)
Mar 2028
Burwell
Other ยท Energy Power Resources Limited
38 MWBuilt Burwell GSP
National Grid (England & Wales)
Peak Gen Makro Exeter
Other ยท Peak Gen Power 14 Limited
20 MWBuilt Exeter 132kV Substation
National Grid (England & Wales)
Glanford
Other ยท Epr Glanford Limited
15 MWBuilt Keadby GSP
National Grid (England & Wales)
Bolney Grid Stability Services
Other ยท Wp Grid Services 13 Limited
0 MWScoping Bolney 400kV Substation
National Grid (England & Wales)
Oct 2031
Cilfynydd Grid Stability Services
Other ยท Cilfynydd Grid Services Limited
0 MWConsents Approved Cilfynydd 400kV Substation
National Grid (England & Wales)
Mar 2027
Eye Grid Services Facility
Other ยท Conrad (Eye) Limited
0 MWConsents Approved Yaxley 400kV Substation
National Grid (England & Wales)
Dec 2025
Lister Drive 275kV
Other ยท Lister Drive Solutions Limited
0 MWBuilt Lister Drive 275kV Substation
National Grid (England & Wales)
Mersey Reactive 1
Other ยท Mersey Reactive Power Limited
0 MWBuilt Frodsham (Network Rail) GSP
National Grid (England & Wales)
Rassau Stability Services Limited
Other ยท WP Grid Services 16 Limited
0 MWScoping Rassau 400kV Substation
National Grid (England & Wales)
Oct 2037
Sellindge Grid Stability Services
Other ยท Sellindge Grid Services Limited
0 MWConsents Approved Sellindge 400kV Substation
National Grid (England & Wales)
Aug 2026
Swansea Greener Grid Park - Connection 2
Other ยท Swansea Grid Solutions Limited
0 MWConsents Approved Swansea North 400kV Substation
National Grid (England & Wales)
Jul 2025
Walpole Grid Services Facility
Other ยท Conrad (Walpole) Limited
0 MWConsents Approved Walpole 400kV Substation
National Grid (England & Wales)
Jul 2026

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed โ€œconnection nodesโ€ are listed but not mapped.