Port of Mostyn

Port of Mostyn is a 140 MW other project in planning, connecting to the National Grid (England & Wales) network at Connah's Quay 400kV Substation, with capacity due from June 2031. The connection agreement is held by Mostyn Seapower Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Jun 2031 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-000421-2
Customer
Mostyn Seapower Limited
Technology
Tidal
Total capacity
140 MW
Change in this agreement
+70 MW
Capacity effective from
1 June 2031
Connection site
Connah's Quay 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near Connah's Quay Β· Grid map

Other projects at Connah's Quay 400kV Substation