🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown12544.1 GW in total
In planning968scoping or awaiting consent
Consented or building149closest to connecting
Built212connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

125 projects · page 1 of 3
ProjectCapacityStageConnection siteFrom
Sizewell C
Nuclear · Sizewell C Limited
3.3 GWConsents Approved Sizewell 400kV Substation
National Grid (England & Wales)
Jul 2036
Hornsea Power Station 3
Offshore wind · Hornsea Project Three (UK) Limited
3.0 GWConsents Approved Norwich Main 400kV Substation
National Grid (England & Wales)
Dec 2028
Hornsea Power Station 3
Offshore wind · Hornsea Project Three (UK) Limited
2.3 GWConsents Approved Norwich Main 400kV Substation
National Grid (England & Wales)
Oct 2026
Damhead Creek 2
Battery storage · VPI Power Limited
1.8 GWConsents Approved Kingsnorth 400kV Substation
National Grid (England & Wales)
Oct 2030
Sizewell C
Nuclear · Sizewell C Limited
1.7 GWConsents Approved Sizewell 400kV Substation
National Grid (England & Wales)
Jul 2035
East Anglia Three
Offshore wind · East Anglia Three Limited
1.3 GWConsents Approved East Anglia Project Three Offshore Platform
National Grid (England & Wales)
Jan 2026
Vanguard
Offshore wind · Norfolk Vanguard West Limited
1.3 GWConsents Approved Necton 400kV Substation
National Grid (England & Wales)
Apr 2028
Vanguard East
Offshore wind · Norfolk Vanguard East Ltd
1.3 GWConsents Approved Necton 400kV Substation
National Grid (England & Wales)
Dec 2028
Dogger Bank Project C
Offshore wind · Doggerbank Offshore Wind Farm Project 3 Projco Limited
1.2 GWConsents Approved Lackenby 400kV Substation
National Grid (England & Wales)
Apr 2025
Gateway Energy Centre Power Station
Battery storage · Gateway Energy Centre Limited
1.0 GWConsents Approved Coryton South 400kV Substation
National Grid (England & Wales)
Oct 2029
NatPower Teesside Green Energy Park
Battery storage · Old Rides Energy Storage Limited
1.0 GWConsents Approved Teeside Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2035
Thornton Facility
Solar + storage · Balwen Limited
930 MWConsents Approved Thornton 400kV Substation
National Grid (England & Wales)
Oct 2032
Fiddlers Ferry BESS
Battery storage · Fiddlers Ferry Ltd
900 MWConsents Approved Fiddlers Ferry 275kV Substation
National Grid (England & Wales)
Oct 2029
Net Zero Teesside Power Project
Gas · Net Zero Teesside Power Limited
860 MWConsents Approved Tod Point 275kV Substation
National Grid (England & Wales)
Jul 2027
Wilton CCGT Project 1
Gas · Sembcorp Utilities (UK) Limited
850 MWConsents Approved Greystones B 275kV Substation
National Grid (England & Wales)
Oct 2035
Spalding Energy Expansion
Battery storage · Spalding Energy Expansion Limited
850 MWConsents Approved Spalding North 400kV Substation
National Grid (England & Wales)
Oct 2030
Flash Solar Farm
Solar + storage · Elements Green Trent Ltd
800 MWConsents Approved Staythorpe 400kV Substation
National Grid (England & Wales)
May 2028
Wilton CCGT Project 2
Gas · Sembcorp Utilities (UK) Limited
700 MWConsents Approved Greystones A 275kV Substation
National Grid (England & Wales)
Oct 2035
Carrington
Battery storage · Carrington Storage Limited
680 MWConsents Approved Carrington 400KV Substation
National Grid (England & Wales)
Oct 2027
Cottam Solar PV + BESS
Solar + storage · Cottam Solar Project Limited
600 MWConsents Approved Cottam 400kV Substation
National Grid (England & Wales)
Sep 2029
Fiddlers Ferry BESS
Battery storage · Fiddlers Ferry Ltd
600 MWConsents Approved Fiddlers Ferry 275kV Substation
National Grid (England & Wales)
Oct 2028
North Killingholme Power Project
Gas · Uniper UK Limited
540 MWConsents Approved Killingholme 400kV Substation
National Grid (England & Wales)
Sep 2030
Cottam
Solar + storage · Gate Burton Energy Park Limited
500 MWConsents Approved Cottam 400kV Substation
National Grid (England & Wales)
Jul 2030
Culham Storage
Battery storage · Culham Storage Limited
500 MWConsents Approved Culham Jet 400kV Substation
National Grid (England & Wales)
Oct 2029
Greta III
Solar + storage · Tagenergy Development UK Limited
500 MWConsents Approved Drakelow 400kV Substation
National Grid (England & Wales)
Oct 2029
Holdsworth Road
Battery storage · Mas 002 Limited
500 MWConsents Approved Bradford West 275kV Substation
National Grid (England & Wales)
Oct 2036
Sunnica
Solar + storage · Sunnica Limited
500 MWConsents Approved South Anglia Connection Node D 400kV Substation
National Grid (England & Wales)
Oct 2030
West Burton Solar Project
Solar + storage · West Burton Solar Project Limited
480 MWConsents Approved West Burton 400kV Substation
National Grid (England & Wales)
Oct 2028
Gateway Energy Centre Power Station
Battery storage · Gateway Energy Centre Limited
450 MWConsents Approved Coryton South 400kV Substation
National Grid (England & Wales)
Jun 2029
Staythorpe (BESS and PV)
Solar + storage · Sse Staythorpe Power Limited
437 MWConsents Approved Staythorpe 400kV Substation
National Grid (England & Wales)
Sep 2028
Chickerell Solar PV & BESS
Battery storage · Chickerell Storage Limited
400 MWConsents Approved Chickerell 400kV Substation
National Grid (England & Wales)
Oct 2028
Jersey Farm BESS
Battery storage · Cse39 Limited
400 MWConsents Approved Jersey Farm 400kV Substation
National Grid (England & Wales)
Oct 2032
Shipley Road BESS
Battery storage · Cse43 Limited
400 MWConsents Approved Sussex and Romney Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2031
Vanguard
Offshore wind · Norfolk Vanguard West Limited
400 MWConsents Approved Necton 400kV Substation
National Grid (England & Wales)
Dec 2027
Vanguard East
Offshore wind · Norfolk Vanguard East Ltd
400 MWConsents Approved Necton 400kV Substation
National Grid (England & Wales)
Apr 2028
Thornton Facility
Solar + storage · Balwen Limited
400 MWConsents Approved Thornton 400kV Substation
National Grid (England & Wales)
Nov 2028
Welbar Energy Storage
Battery storage · Welbar Energy Storage Limited
400 MWConsents Approved Hams Hall 400kV Substation
National Grid (England & Wales)
Oct 2032
Flash Solar Farm
Solar + storage · Elements Green Trent Ltd
360 MWConsents Approved Staythorpe 400kV Substation
National Grid (England & Wales)
May 2027
Pembroke BESS
Battery storage · RWE Generation UK Plc
350 MWConsents Approved Pembroke 400kV Substation
National Grid (England & Wales)
May 2029
Monk Fryston SSE
Battery storage · Sse Battery Monk Fryston Limited
320 MWConsents Approved Monk Fryston 275kV Substation
National Grid (England & Wales)
Oct 2025
BOOM Power Llanbabo Generation
Battery storage · Carrog Storage Facility Limited
300 MWConsents Approved Wylfa 400kV Substation
National Grid (England & Wales)
Oct 2028
Bramford BESS
Battery storage · Cse33 Limited
300 MWConsents Approved Bramford 400kV Substation
National Grid (England & Wales)
Nov 2029
Didcot Road
Battery storage · Didcot BESS Limited
300 MWConsents Approved Didcot 400kV Substation
National Grid (England & Wales)
Oct 2028
Fiddlers Ferry BESS
Battery storage · Fiddlers Ferry Ltd
300 MWConsents Approved Fiddlers Ferry 275kV Substation
National Grid (England & Wales)
Oct 2027
Exeter BESS
Battery storage · Exeter Storage Limited
290 MWConsents Approved Exeter 400kV Substation
National Grid (England & Wales)
Aug 2027
Pembroke BESS
Battery storage · RWE Generation UK Plc
285 MWConsents Approved Pembroke 400kV Substation
National Grid (England & Wales)
Mar 2029
Al Boum Photo (Norton)
Battery storage · Al Boum Photo Ltd
275 MWConsents Approved Norton 400kV Substation
National Grid (England & Wales)
Oct 2031
Cottam
Solar + storage · Gate Burton Energy Park Limited
250 MWConsents Approved Cottam 400kV Substation
National Grid (England & Wales)
Oct 2029
Hookers Farm BESS
Battery storage · Ancleggan Limited
250 MWConsents Approved Bolney 132kV Substation
National Grid (England & Wales)
Oct 2031
Sheaf Energy
Battery storage · Sheaf Energy Limited
249 MWConsents Approved Richborough 400kV Substation
National Grid (England & Wales)
Apr 2025
Page 1 of 3

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.