Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· NGETHookers Farm BESS
Hookers Farm BESS is a 250 MW battery storage project consented, connecting to the National Grid (England & Wales) network at Bolney 132kV Substation, with capacity due from October 2031. The connection agreement is held by Ancleggan Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Oct 2031 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-002308
- Customer
- Ancleggan Limited
- Technology
- Energy Storage System
- Total capacity
- 250 MW
- Change in this agreement
- +250 MW
- Capacity effective from
- 31 October 2031
- Connection site
- Bolney 132kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Consents Approved
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Bolney 132kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem