Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue on the SSEN Transmission (north Scotland) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown444102.5 GW in total
In planning303scoping or awaiting consent
Consented or building52closest to connecting
Built89connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

444 projects · page 6 of 9
ProjectCapacityStageConnection siteFrom
Corriegarth 2 Wind Farm
Onshore wind · Corriegarth 2 Wind Farm Limited
70 MWScoping Corriegarth 132/33kV substation
SSEN Transmission (north Scotland)
Jul 2027
Tormsdale Windfarm
Solar + storage · Asuk Holdco 1 Limited
70 MWScoping Mybster 3 132/33kV Substation
SSEN Transmission (north Scotland)
Jun 2028
Corriegarth
Onshore wind · Corriegarth Wind Energy Limited
69 MWBuilt Corriegarth 132/33kV substation
SSEN Transmission (north Scotland)
Lochluichart
Onshore wind · Lzn Limited
69 MWBuilt Corriemoillie 132kV Substation
SSEN Transmission (north Scotland)
Correen Hills Wind Farm
Onshore wind · Edf Energy Renewables Limited
68 MWScoping Correen Hills Wind Farm 132kV Substation
SSEN Transmission (north Scotland)
Sep 2031
Ladyfield Renewable Energy Park
Battery storage · Ladyfield Renewable Energy Park Ltd
68 MWScoping Creag Dhubh 275/132/33kV
SSEN Transmission (north Scotland)
Oct 2029
Strathy North Wind
Onshore wind · Strathy Wind Farm Limited
68 MWBuilt Strathy North 132/33kV Substation
SSEN Transmission (north Scotland)
Blarghour Wind
Onshore wind · Blarghour Wind Farm Limited
67 MWConsents Approved Blarghour Substation
SSEN Transmission (north Scotland)
Apr 2029
Cairn Duhie Wind Farm
Onshore wind · Cairn Duhie Energy Limited
67 MWConsents Approved Berryburn 275/33kV GSP Substation
SSEN Transmission (north Scotland)
Oct 2028
Bilbo Farm
Solar + storage · Lel Bilbo Solar Limited
67 MWScoping Strichen 132/33kV GSP Substation
SSEN Transmission (north Scotland)
Oct 2033
Berry Burn Wind Farm
Onshore wind · Berry Burn Wind Farm Limited
67 MWBuilt Berry Burn GSP
SSEN Transmission (north Scotland)
Kilbraur Wind Farm
Onshore wind · Kilbraur Wind Energy Limited
67 MWBuilt Kilbraur Wind Farm Substation
SSEN Transmission (north Scotland)
Heastabhal Wind Farm
Onshore wind · RWE Renewables UK Onshore Wind Limited
66 MWScoping Heastabhal Wind Farm Substation 132 KV
SSEN Transmission (north Scotland)
Oct 2033
Millennium Wind
Onshore wind · Millennium Wind Energy Limited
65 MWBuilt Millennium GSP
SSEN Transmission (north Scotland)
Allt Domhain Wind Farm
Onshore wind · Energyfarm Allt Domhain Ltd
65 MWScoping Carradale 3 132/33Kv Grid Supply Point Substation
SSEN Transmission (north Scotland)
Oct 2035
Strathy Wood Wind Farm
Onshore wind · RWE Renewables UK Onshore Wind Limited
64 MWConsents Approved Strathy Wood 132/33kV Substation
SSEN Transmission (north Scotland)
Dec 2029
Clashindarroch 2
Onshore wind · Vattenfall Wind Power Ltd
63 MWUnder Construction/Commissioning Cairnford GSP
SSEN Transmission (north Scotland)
Jun 2027
Tomchrasky Wind Farm
Onshore wind · E Power Limited
63 MWConsents Approved Tomchrasky Wind Farm 132/33kV Substation
SSEN Transmission (north Scotland)
Mar 2032
Clunie (part of the Clunie Cascade)
Hydro and pumped storage · Sse Generation Limited
61 MWBuilt Clunie GSP
SSEN Transmission (north Scotland)
Crakaig Wind Energy Hub
Wind + storage · Crakaig Wind Energy Hub Limited
60 MWScoping Brora 132/33Kv Grid Supply Point Substation
SSEN Transmission (north Scotland)
Oct 2034
Killean Wind Farm
Onshore wind · Renewable Energy Systems Limited
60 MWScoping Carradale 3 132/33Kv Grid Supply Point Substation
SSEN Transmission (north Scotland)
Oct 2034
Kirkton Wind Farm
Onshore wind · Kirkton Wind Farm Limited
60 MWAwaiting Consents Connagill 275kV Substation
SSEN Transmission (north Scotland)
Oct 2029
Moy Wind Farm
Onshore wind · Eneco Moy Limited
60 MWBuilt Inverness GSP
SSEN Transmission (north Scotland)
Balnespick Wind Farm
Wind + storage · Fred Olsen Renewables Limited
58 MWScoping Balnespick Wind Farm 132kV/33kV Substation
SSEN Transmission (north Scotland)
Oct 2032
Beinn Ghlas
Onshore wind · Headwind Development Services Limited
58 MWAwaiting Consents Taynuilt GSP
SSEN Transmission (north Scotland)
Oct 2034
Melvich Wind Energy Hub
Wind + storage · Melvich Wind Energy Hub Limited
58 MWAwaiting Consents Melvich Community Wind Farm 132/33kV Substation
SSEN Transmission (north Scotland)
Apr 2030
Leuchland Energy Centre A
Solar + storage · Leuchland Energy Centre Limited
57 MWScoping Leuchland Farm IDNO
SSEN Transmission (north Scotland)
Oct 2033
Leuchland Energy Centre B
Solar + storage · Leuchland Energy Centre Limited
57 MWScoping Leuchland Farm IDNO
SSEN Transmission (north Scotland)
Oct 2033
High Brenfield 1
Onshore wind · High Brenfield Wind Farm Limited
53 MWScoping Craig Murrail 275/33kV GSP Substation
SSEN Transmission (north Scotland)
Oct 2034
Watten Wind Farm
Onshore wind · Edf Energy Renewables Limited
53 MWScoping Mybster 3 132/33kV Substation
SSEN Transmission (north Scotland)
Jun 2028
Baillie Wind Farm
Onshore wind · Baillie Windfarm Limited
53 MWBuilt Dounreay GSP
SSEN Transmission (north Scotland)
Lochay (Part of Killin Cascade Hydro Scheme)
Hydro and pumped storage · Sse Generation Limited
51 MWUnder Construction/Commissioning Lochay 132/11kV Substation
SSEN Transmission (north Scotland)
Jan 2027
50MW BESS Connagill
Battery storage · Cerulisia Ltd
50 MWScoping New Connagill 275/132kV Substation
SSEN Transmission (north Scotland)
Oct 2031
Allt an Tuir Renewable Energy Park
Solar + storage · Allt An Tuir Renewable Energy Park Limited
50 MWScoping Shin 1 GSP
SSEN Transmission (north Scotland)
Jun 2031
Aultcraggie BESS
Battery storage · Opde UK Limited
50 MWScoping Brora GSP
SSEN Transmission (north Scotland)
Oct 2034
Beinn an Tuirc 3
Onshore wind · Scottish Power Renewables (UK) Limited
50 MWBuilt Carradale 1 GSP
SSEN Transmission (north Scotland)
Breakish Windfarm
Onshore wind · Asuk Holdco 2 Limited
50 MWScoping Breakish 132kV Substation
SSEN Transmission (north Scotland)
May 2029
Garlogie B-1
Solar + storage · Garlogie Energy Centre Limited
50 MWScoping Garlogie Production B 275/33kV GSP
SSEN Transmission (north Scotland)
Oct 2033
Garlogie B-2
Solar + storage · Garlogie Energy Centre Limited
50 MWScoping Garlogie Production B 275/33kV GSP
SSEN Transmission (north Scotland)
Oct 2033
Garlogie C-1
Solar + storage · Garlogie Energy Centre Limited
50 MWScoping Garlogie Production C 275/33kV GSP
SSEN Transmission (north Scotland)
Oct 2033
Garlogie C-2
Solar + storage · Garlogie Energy Centre Limited
50 MWScoping Garlogie Production C 275/33kV GSP
SSEN Transmission (north Scotland)
Oct 2033
Garlogie PV and BESS A-1
Solar + storage · Garlogie Energy Centre Limited
50 MWScoping Garlogie Production A 275/33kV GSP
SSEN Transmission (north Scotland)
Oct 2033
Garlogie PV and BESS A-2
Solar + storage · Garlogie Energy Centre Limited
50 MWScoping Garlogie Production A 275/33kV GSP
SSEN Transmission (north Scotland)
Oct 2033
High Constellation Windfarm
Onshore wind · High Constellation Windfarm Limited
50 MWConsents Approved High Constellation 132/33kV Substation
SSEN Transmission (north Scotland)
Oct 2028
Jamesfield 3
Battery storage · Harmony Energy Limited
50 MWScoping New Abernethy 132kV
SSEN Transmission (north Scotland)
Oct 2037
Lairg II Wind Farm
Onshore wind · Lairg II LLP
50 MWConsents Approved Lairg GSP
SSEN Transmission (north Scotland)
Jul 2027
Learney BESS
Battery storage · Igp Solar 22 Limited
50 MWScoping Learney BESS 132Kv
SSEN Transmission (north Scotland)
Oct 2032
Locharber
Solar + storage · Lochaber Energy Centre Limited
50 MWScoping Arbroath GSP
SSEN Transmission (north Scotland)
Oct 2032
Nether Pitforthie BESS
Battery storage · Opdenergy UK 14 Limited
50 MWScoping Fiddes 275/33Kv Grid Supply Point Substation
SSEN Transmission (north Scotland)
Oct 2032
Newton of Park BESS 2
Battery storage · Opdenergy UK 16 Limited
50 MWScoping Nairn 132/33kV Grid Supply Point Substation
SSEN Transmission (north Scotland)
Jan 2028

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.