Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· SHETLearney BESS
Learney BESS is a 50 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Learney BESS 132Kv, with capacity due from October 2032. The connection agreement is held by Igp Solar 22 Limited.
Project stageIn planning
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2032 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003241
- Customer
- Igp Solar 22 Limited
- Technology
- Energy Storage System
- Total capacity
- 50 MW
- Change in this agreement
- +50 MW
- Capacity effective from
- 1 October 2032
- Connection site
- Learney BESS 132Kv
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem