Grid infrastructure › Connection queue › Wind + storage
WIND + STORAGE · SHETMelvich Wind Energy Hub
Melvich Wind Energy Hub is a 58 MW wind + storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Melvich Community Wind Farm 132/33kV Substation, with capacity due from April 2030. The connection agreement is held by Melvich Wind Energy Hub Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Apr 2030 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-001688
- Customer
- Melvich Wind Energy Hub Limited
- Technology
- Energy Storage System, Wind Onshore
- Total capacity
- 58 MW
- Change in this agreement
- +58 MW
- Capacity effective from
- 1 April 2030
- Connection site
- Melvich Community Wind Farm 132/33kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Awaiting Consents
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Projects connecting near Melvich Community Wind Farm · Grid map
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem