Grid infrastructure › Connection queue › Onshore wind

ONSHORE WIND · SHET

Clashindarroch 2

Clashindarroch 2 is a 63 MW onshore wind project under construction or commissioning, connecting to the SSEN Transmission (north Scotland) network at Cairnford GSP, with capacity due from June 2027. The connection agreement is held by Vattenfall Wind Power Ltd.

Project stageUnder construction
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingFrom Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000041
Customer
Vattenfall Wind Power Ltd
Technology
Wind Onshore
Total capacity
63 MW
Change in this agreement
+63 MW
Capacity effective from
4 June 2027
Connection site
Cairnford GSP
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Under Construction/Commissioning
Connections reform gate
Gate 2

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Cairnford GSP · Grid map

Other projects at Cairnford GSP

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem