Newton of Park BESS 2

Newton of Park BESS 2 is a 50 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Nairn 132/33kV Grid Supply Point Substation, with capacity due from January 2028. The connection agreement is held by Opdenergy UK 16 Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Jan 2028 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-003562
Customer
Opdenergy UK 16 Limited
Technology
Energy Storage System
Total capacity
50 MW
Change in this agreement
+50 MW
Capacity effective from
31 January 2028
Connection site
Nairn 132/33kV Grid Supply Point Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Nairn · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem