๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Solar interconnection queue in the USA (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown16419.3 GW
Active in queue19.3 GW164 requests
Agreement signed11.6 GW93 requests
Withdrawn78365.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

164 requests ยท page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-652, Sumter County
Solar
615 MWAgreement signed Sumter, GASoutheast Sep 2017target 2023
Solar project GEN-2017-195, Johnson County
Solar
500 MWAgreement signed Johnson, KSSPP Nov 2017target 2030
Solar project GEN-2017-108, Henry County
Solar
400 MWAgreement signed Henry, MOSPP Aug 2017target 2027
Solar project GEN-2017-184, Hodgeman County
Solar
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Cottonwood Bayou Solar
Solar ยท Cottonwood Bayou Solar, LLC
351 MWAgreement signed Brazoria, TXERCOT Sep 2017target 2026
Myrtle Solar
Solar ยท Myrtle Solar, LLC
321 MWAgreement signed Brazoria, TXERCOT Mar 2017target 2026
Solar project GEN-2017-210, Cedar County
Solar
310 MWPaused / redesign Cedar, NESPP Nov 2017target 2026
Horseshoe Bend Solar
Solar ยท Clenera
301 MWIn study Brown, TXERCOT Jun 2017target 2027
Solar project GEN-2017-239, Yoakum County
Solar
300 MWAgreement signed Yoakum, TXSPP Nov 2017target 2026
Macadamia Solar
Solar
300 MWAgreement signed Washington, NCPJM Sep 2017target 2028
Solar project J813, Clay County
Solar
275 MWUnder construction Clay, ILMISO Jun 20172024
Solar project J815, Christian County
Solar
250 MWUnder construction Christian, ILMISO Jun 2017target 2022
Solar project J877, Palo Alto County
Solar
250 MWUnder construction Palo Alto, IAMISO Jun 2017target 2023
Solar project GEN-2017-150, Grady County
Solar
250 MWAgreement signed Grady, OKSPP Nov 2017target 2026
Solar project GEN-2017-164, Garfield County
Solar
250 MWAgreement signed Garfield, OKSPP Nov 20172025
Solar project J829, Sullivan County
Solar
250 MWUnder construction Sullivan, INMISO Jun 2017target 2022
Solar project J800, White County
Solar
250 MWUnder construction White, ILMISO Jun 20172024
Solar project GEN-2017-141, Wagoner County
Solar
242 MWAgreement signed Wagoner, OKSPP Nov 2017target 2027
Sycamore Cross Solar
Solar
240 MWAgreement signed Isle Of Wight, VAPJM Mar 2017target 2026
South Branch Solar
Solar
205 MWPaused / redesign Hancock, OHPJM Aug 2017target 2025
Solar project GEN-2017-226, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Solar project GEN-2017-220, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2026
Solar project GEN-2017-040, Ochiltree County
Solar
200 MWAgreement signed Ochiltree, TXSPP May 2017target 2026
Solar project GEN-2017-075, Johnston County
Solar
200 MWAgreement signed Johnston, OKSPP May 2017target 2026
Trade Post Solar Energy Center
Solar
200 MWAgreement signed Sullivan, INPJM Mar 2017target 2026
Solar project J934, Crittenden County
Solar
200 MWUnder construction Crittenden, ARMISO Jun 20172024
Rodeo Solar
Solar ยท Core Solar SPV I, LLC
200 MWAgreement signed Andrews, TXERCOT Jun 2017target 2026
Anson Solar Center, Phase III
Solar ยท Anson Solar Center 3, LLC
200 MWIn study Jones, TXERCOT Jun 2017target 2027
Solar project GEN-2017-092, Muskogee County
Solar
200 MWAgreement signed Muskogee, OKSPP May 2017target 2026
Solar project J878, Kenosha County
Solar
200 MWUnder construction Kenosha, WIMISO Jun 20172024
Solar project J805, Shelby County
Solar
199 MWUnder construction Shelby, INMISO Jun 2017target 2022
Solar project J799, Washtenaw County
Solar
189 MWUnder construction Washtenaw, MIMISO Jun 2017target 2021
Solar project GEN-2017-018, Barber County
Solar
189 MWAgreement signed Barber, KSSPP May 20172025
Azalea Springs Solar
Solar ยท AZALEA SPRINGS SOLAR PARK LLC
181 MWAgreement signed Angelina, TXERCOT Jul 2017target 2025
Solar project J919, Jackson County
Solar
180 MWUnder construction Jackson, ARMISO Jun 20172023
Gateway Solar Energy Center
Solar ยท Gateway Solar Energy Center, LLC
180 MWIn study St. Lawrence, NYNYISO Mar 2017target 2028
Bestla Solar
Solar
180 MWPaused / redesign Winkler, TXERCOT Jan 2017
Kingwood Solar
Solar
175 MWAgreement signed Greene, OHPJM Sep 2017target 2026
Solar project GEN-2017-140, Wagoner County
Solar
160 MWAgreement signed Wagoner, OKSPP Nov 2017target 2027
Solar project GEN-2017-011, Ellis County
Solar
152 MWAgreement signed Ellis, OKSPP May 2017target 2026
Solar project J875, Lenawee County
Solar
150 MWUnder construction Lenawee, MIMISO Jun 2017target 2022
Spring Grove Solar II
Solar
150 MWAgreement signed Surry, VAPJM Jun 2017target 2025
Solar project GEN-2017-171, Comanche County
Solar
150 MWAgreement signed Comanche, OKSPP Nov 2017target 2027
Wild Indigo Solar
Solar
150 MWPaused / redesign Surry, VAPJM Oct 2017target 2026
Riverstart Solar Park IV
Solar
150 MWAgreement signed Randolph, INPJM Sep 2017target 2025
Solar project J874, Murray County
Solar
150 MWUnder construction Murray, MNMISO Jun 2017target 2024
Solar project GEN-2017-187, Terry County
Solar
150 MWAgreement signed Terry, TXSPP Nov 2017target 2026
Solar project J859, Cass County
Solar
150 MWUnder construction Cass, ILMISO Jun 2017target 2022
Solar project J818, Jefferson County
Solar
149 MWUnder construction Jefferson, WIMISO Jun 2017target 2022
Blue Jay Solar
Solar ยท Blue Jay Solar I, LLC
141 MWAgreement signed Grimes, TXERCOT May 2017target 2025
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)