United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2014 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Nuclear project J371, Ogle County Nuclear |
2,325 MW | Withdrawn / abandoned |
| Hatfield Ferry, Units 1, 2, and 3 Coal |
1,710 MW | Withdrawn / abandoned |
| Nuclear project J372, Rock Island County Nuclear |
1,373 MW | Withdrawn / abandoned |
| Gas project 251, Tipton County Gas |
1,156 MW | Withdrawn / abandoned |
| Rockwood G Gas ยท Lincoln Clean |
1,122 MW | Withdrawn / abandoned |
| Gas project J404, Jefferson Parish County Gas |
1,078 MW | Withdrawn / abandoned |
| Gas project AA2-035, Grundy County Gas |
1,019 MW | Withdrawn / abandoned |
| Gas project J425, St. Charles Parish County Gas |
999 MW | Withdrawn / abandoned |
| Gas project J402, Orleans Parish County Gas |
991 MW | Withdrawn / abandoned |
| Shawnee G Gas ยท Lincoln Clean |
928 MW | Withdrawn / abandoned |
| Mira Loma Hybrid Power Project Gas |
910 MW | Withdrawn / abandoned |
| Viejo Hybrid Power Gas |
910 MW | Withdrawn / abandoned |
| Eagle Mountain SES Gas ยท Luminant |
853 MW | Withdrawn / abandoned |
| Gas project J336, Calumet County Gas |
845 MW | Withdrawn / abandoned |
| Gas project J338, Winnebago County Gas |
845 MW | Withdrawn / abandoned |
| Combined Cycle Gas |
837 MW | Withdrawn / abandoned |
| Gas project J355, Adair County Gas |
810 MW | Withdrawn / abandoned |
| Gas project J363, Pottawattamie County Gas |
810 MW | Withdrawn / abandoned |
| Gas project Z2-026, Berks County Gas |
800 MW | Withdrawn / abandoned |
| Gas project GI-1407, Emmons County Gas |
800 MW | Withdrawn / abandoned |
| Gas project J388, Vermilion County Gas |
800 MW | Withdrawn / abandoned |
| Gas project AA1-048, Grundy County Gas |
800 MW | Withdrawn / abandoned |
| Gas project GI-1408, Emmons County Gas |
800 MW | Withdrawn / abandoned |
| Site C Brazos G Gas ยท Brazos Elec Coop |
800 MW | Withdrawn / abandoned |
| Gas project GEN-2014-018, Nacogdoches County Gas |
757 MW | Withdrawn / abandoned |
| Gas project J353, Dickinson County Gas |
725 MW | Withdrawn / abandoned |
| Santa Ana Energy Center Gas |
700 MW | Withdrawn / abandoned |
| Gas project Z2-064, Washington County Gas |
651 MW | Withdrawn / abandoned |
| Birch Street Generation Facility (Fka Birch Street- Simple Cycle) Gas |
625 MW | Withdrawn / abandoned |
| Grand Ave Generation Facility (Fka Grand Ave Simple Cycle) Gas |
625 MW | Withdrawn / abandoned |
| Wind Onshore wind |
601 MW | Withdrawn / abandoned |
| Wind Onshore wind |
601 MW | Withdrawn / abandoned |
| Hydro project G0502, Elmore County Hydro |
600 MW | Withdrawn / abandoned |
| Onshore wind project GI-1405, Banner County Onshore wind |
600 MW | Withdrawn / abandoned |
| Battery storage project 176, Meagher County Battery storage |
600 MW | Withdrawn / abandoned |
| Union Valley G Gas ยท Quantum |
592 MW | Withdrawn / abandoned |
| Clear Springs G Gas ยท Quantum |
592 MW | Withdrawn / abandoned |
| Gas project J383, Manitowoc County Gas |
571 MW | Withdrawn / abandoned |
| Other project AA1-090 Other |
565 MW | Withdrawn / abandoned |
| Gas project AA1-098, Middlesex County Gas |
560 MW | Withdrawn / abandoned |
| Gas project J337, Winnebago County Gas |
551 MW | Withdrawn / abandoned |
| Gas project J335, Calumet County Gas |
551 MW | Withdrawn / abandoned |
| Gas project J389, Rock County Gas |
550 MW | Withdrawn / abandoned |
| Van Alstyne G Gas ยท Navasota |
548 MW | Withdrawn / abandoned |
| Nci Hybrid Power Solar + storage |
538 MW | Withdrawn / abandoned |
| Cci Hybrid Power Gas |
508 MW | Withdrawn / abandoned |
| Halyard Henderson Gas ยท Halyard Energy |
484 MW | Withdrawn / abandoned |
| Simple Cycle Gas |
478 MW | Withdrawn / abandoned |
| Gas project GEN-2014-017, Nacogdoches County Gas |
477 MW | Withdrawn / abandoned |
| Lake Creek 3 G Gas ยท Luminant |
471 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)77 ยท 22.8 GW
- PJM (Mid-Atlantic, Midwest)126 ยท 12.4 GW
- ERCOT (Texas)52 ยท 12.1 GW
- CAISO (California)70 ยท 10.2 GW
- West (non-ISO utilities)151 ยท 9,551 MW
- SPP (Southwest Power Pool)56 ยท 8,704 MW
- Southeast (non-ISO utilities)76 ยท 6,064 MW
- ISO-NE (New England)28 ยท 4,881 MW
- NYISO (New York)30 ยท 1,581 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)