Queue requests in study in the USA (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown29757.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

297 requests ยท page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project G0648, Klamath County
Solar + storage
1,400 MWIn study Klamath, ORWest May 2020target 2026
Replace 1163.3 MW of Sabine Units 3, 4 & 1 with 2 on 1 Combined Cycle Gas Turbine facility; Sabine 1
Gas
1,166 MWIn study Orange, TXMISO Aug 2020target 2026
Solar + storage project G0657, Klamath County
Solar + storage
1,000 MWIn study Klamath, ORWest Sep 2020target 2027
Arida 3 Solar Farm
Solar + storage
900 MWIn study Clark, NVCAISO Apr 2020target 2030
Solar + storage project Q76, Kern County
Solar + storage
800 MWIn study Kern, CAWest Mar 2020target 2023
Onshore wind project 391
Onshore wind
750 MWPaused / redesign West Aug 2020target 2023
Onshore wind project C012, Wheatland County
Onshore wind
750 MWIn study Wheatland, MTWest Jul 2020target 2023
Sunrise Power Improvement
Gas
656 MWIn study Kern, CACAISO Apr 2020target 2024
Harquahala Sunrise
Solar + storage
618 MWIn study Maricopa, AZCAISO Apr 2020target 2030
Skylab Solar
Solar ยท EDF Renewables Development, Inc.
610 MWIn study Wharton, TXERCOT Jun 2020target 2025
Battery storage project G0642, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2025
Battery storage project G0643, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2024
Old Aqueduct Solar
Solar + storage ยท Old Aqueduct Solar
512 MWIn study Hale, TXERCOT Dec 2020target 2028
Tabor Solar
Solar ยท Quanah Solar LLC
506 MWIn study Hardeman, TXERCOT Sep 2020target 2027
Frye Storage
Solar + storage ยท Hecate Energy Frye Storage LLC
504 MWIn study Swisher, TXERCOT Sep 2020target 2026
Pinnington Storage
Solar + storage ยท Hecate Energy Longhorn Storage LLC
503 MWIn study Jack, TXERCOT Dec 2020target 2029
Solar + storage project Q334, Maricopa County
Solar + storage
500 MWIn study Maricopa, AZWest Mar 2020target 2023
Other project 390, Yellowstone County
Other
500 MWIn study Yellowstone, MTWest Aug 2020target 2023
Solar + storage project 84, Pima County
Solar + storage
500 MWIn study Pima, AZWest Sep 2020target 2023
Battery storage project Q78, Kern County
Battery storage
500 MWIn study Kern, CAWest Oct 2020target 2021
Battery storage project G0656, Grant County
Battery storage
500 MWIn study Grant, WAWest Sep 2020target 2023
Solar project GEN-2020-087, Comanche County
Solar
500 MWIn study Comanche, OKSPP Apr 2020target 2026
Hawkins Solar Hybrid
Solar + storage
500 MWIn study Kern, CACAISO Apr 2020target 2027
Dolphin Solar
Solar ยท Dolphin Solar LLC
450 MWIn study Fountain, INPJM Sep 2020target 2024
Solar + storage project Q337, Yavapai County
Solar + storage
450 MWIn study Yavapai, AZWest Mar 2020target 2027
Solar + storage project Q352, Navajo County
Solar + storage
450 MWIn study Navajo, AZWest Sep 2020target 2023
Solar + storage project Company 191, Clark County
Solar + storage
425 MWPaused / redesign Clark, NVWest Aug 2020target 2022
Dragan Storage
Solar + storage ยท Hecate Grid Dragan Storage LLC
408 MWIn study Comanche, TXERCOT Aug 2020target 2026
Mineral Basin Solar Power
Solar ยท Mineral Basin Solar Power, LLC
402 MWIn study Clearfield, PANYISO Aug 2020target 2028
Sequoia
Solar + storage
400 MWIn study Tulare, CACAISO Apr 2020target 2031
Solar project G0651, Lake County
Solar
400 MWIn study Lake, ORWest Jul 2020target 2023
Onshore wind project GEN-2020-067, Terry County
Onshore wind
353 MWIn study Terry, TXSPP Apr 2020target 2026
Onshore wind project Q347, Navajo County
Onshore wind
345 MWIn study Navajo, AZWest Sep 2020target 2024
Gas project J1839, Macon County
Gas
340 MWIn study Macon, ILMISO Jun 2020target 2026
Replace 330 MW of CLECO.DPS Unit with solar; Dolet Hills
Other
330 MWIn study De Soto Parish, LAMISO Dec 2020target 2024
Solar + storage project GEN-2020-011, Phelps County
Solar + storage
320 MWIn study Phelps, NESPP Apr 2020target 2028
Solar + storage project Q359, Pinal County
Solar + storage
315 MWIn study Pinal, AZWest Sep 2020target 2023
Mensa BESS
Battery storage ยท BRP Mensa BESS LLC
307 MWIn study Pecos, TXERCOT Jun 2020target 2027
Old Aqueduct Batt
Solar + storage ยท Old Aqueduct LLC
303 MWIn study Hale, TXERCOT May 2020target 2028
Brantley Branch Batt
Battery storage ยท Brantley Branch LLC
302 MWIn study Rusk, TXERCOT May 2020target 2029
BRP Passu BESS
Battery storage ยท BRP Passu BESS LLC
302 MWIn study Wilbarger, TXERCOT Dec 2020target 2028
Crater BESS
Battery storage ยท BRP Crater BESS LLC
302 MWIn study Howard, TXERCOT May 2020target 2028
Quela BESS
Battery storage ยท BRP Quela BESS LLC
301 MWIn study Bexar, TXERCOT Sep 2020target 2027
Pleasant Grove Solar
Solar ยท Deriva Energy Solar, LLC
300 MWIn study Mchenry, ILPJM Mar 2020target 2023
Butterfly Meadows
Solar ยท Butterfly Meadows Solar Project, LLC
300 MWIn study Van Wert, OHPJM Sep 2020target 2024
Other project Q348, Coconino County
Other
300 MWIn study Coconino, AZWest Sep 2020target 2024
Solar project J1710, Lee County
Solar
300 MWIn study Lee, ARMISO Jun 2020target 2026
Solar + storage project Company 189, Clark County
Solar + storage
300 MWPaused / redesign Clark, NVWest Feb 2020target 2025
Solar project J1712, Perry County
Solar
300 MWIn study Perry, ILMISO Jun 2020target 2025
Other project 78, Apache County
Other
300 MWIn study Apache, AZWest Feb 2020target 2023
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)