United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown10618.1 GW
Active in queue25.8 GW162 requests
Agreement signed18.1 GW106 requests
Withdrawn1,194150.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

106 requests ยท page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Vineyard Offshore Wind
Offshore wind
800 MWAgreement signed MAISO-NE Nov 2016target 2026
Daylight
Solar + storage
611 MWAgreement signed Kings, CACAISO May 2016target 2028
Onshore wind project GI-2016-3, Lincoln County
Onshore wind
600 MWAgreement signed Lincoln, COWest Feb 2016target 2018
Solar project G0539, Deschutes County
Solar
600 MWAgreement signed Deschutes, ORWest May 2016target 2022
Onshore wind project GEN-2016-119, Kingfisher County
Onshore wind
600 MWAgreement signed Kingfisher, OKSPP Nov 20162025
Solar + storage project 838, Utah County
Solar + storage ยท Faraday Interconnection LLC
525 MWAgreement signed Utah, UTWest Dec 2016target 2025
Daggett Solar 3
Solar + storage
522 MWAgreement signed San Bernardino, CACAISO May 2016target 2023
Onshore wind project GI-2016-14, Cheyenne County
Onshore wind
500 MWAgreement signed Cheyenne, COWest Jul 20162020
Pluot
Solar + storage
479 MWAgreement signed Kings, CACAISO May 2016target 2026
Pomegranate
Solar + storage
479 MWAgreement signed Kings, CACAISO May 2016target 2025
Onshore wind project IA-PNM-2016-02, Torrance Cty County
Onshore wind ยท Pacific Wind Development
402 MWAgreement signed Torrance Cty, NMWest May 2016target 2020
Solar + storage project 787, Emery County
Solar + storage ยท Green River Solar I, LLC
400 MWAgreement signed Emery, UTWest Aug 2016target 2024
Onshore wind project 836, Carbon County
Onshore wind ยท PacifiCorp
400 MWAgreement signed Carbon, WYWest Dec 2016target 2027
Onshore wind project GEN-2016-141, Texas County
Onshore wind
350 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-142, Texas County
Onshore wind
350 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Chickahominy Solar 1 and 2
Solar
320 MWAgreement signed Charles City, VAPJM Oct 20162021
Corby
Battery storage
314 MWAgreement signed Solano, CACAISO May 2016target 2027
Canyon Wind
Onshore wind ยท Canyon Wind Energy, LLC
309 MWAgreement signed Scurry, TXERCOT May 2016target 2025
Roccasecca BESS
Battery storage
303 MWAgreement signed Clark, NVCAISO May 2016target 2026
Onshore wind project GEN-2016-111, Mcpherson County
Onshore wind
302 MWAgreement signed Mcpherson, KSSPP Nov 2016target 2027
Onshore wind project GI-2016-4, Lincoln County
Onshore wind
300 MWAgreement signed Lincoln, COWest Feb 2016target 2018
Tahoe
Battery storage
300 MWAgreement signed Clark, NVCAISO May 2016target 2026
Onshore wind project GI-53, Nodaway County
Onshore wind
238 MWAgreement signed Nodaway, MOSoutheast May 2016target 2018
Cherrywood Solar I
Solar
202 MWAgreement signed Caroline, MDPJM Feb 2016target 2026
Onshore wind project GEN-2016-004, Oliver County
Onshore wind
202 MWAgreement signed Oliver, NDSPP Mar 2016target 2027
Tri-X Solar 1 SLF
Solar + storage ยท Crane I Solar Electric, LLC
202 MWAgreement signed Crane, TXERCOT Nov 2016target 2027
Onshore wind project GEN-2016-074, Custer County
Onshore wind
200 MWAgreement signed Custer, NESPP Apr 2016target 2027
Monte Alto 2 Wind
Onshore wind ยท Terra-Gen
200 MWAgreement signed Willacy, TXERCOT Nov 2016target 2027
Solar project IC-441, Decatur County
Solar
189 MWAgreement signed Decatur, GASoutheast Feb 2016target 2028
Onshore wind project GEN-2016-133, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-134, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-138, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-137, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Pastoria Solar
Solar + storage
187 MWAgreement signed Kern, CACAISO May 2016target 2026
Maryneal Wind
Onshore wind ยท Maryneal Windpower, LLC
182 MWAgreement signed Nolan, TXERCOT May 20162021
Cherry Solar
Solar
180 MWAgreement signed Northampton, NCPJM Oct 2016target 2025
Solar project 823, Emery County
Solar ยท PacifiCorp Energy Supply Management
178 MWAgreement signed Emery, UTWest Nov 2016target 2027
Onshore wind project GEN-2016-128, Alfalfa County
Onshore wind
176 MWAgreement signed Alfalfa, OKSPP Nov 2016target 2026
Grandfalls Solar
Solar + storage ยท Nextera
176 MWAgreement signed Upton, TXERCOT May 2016target 2027
Onshore wind project GEN-2016-146, Texas County
Onshore wind
175 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-145, Texas County
Onshore wind
175 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Solar project J643, Jasper County
Solar
175 MWAgreement signed Jasper, INMISO May 20162023
Solar project J586, Mississippi County
Solar
175 MWAgreement signed Mississippi, ARMISO May 20162024
Onshore wind project GEN-2016-102, Pontotoc County
Onshore wind
148 MWAgreement signed Pontotoc, OKSPP Nov 20162025
Solar project 305, Fayette County
Solar
147 MWAgreement signed Fayette, TNSoutheast Nov 2016target 2026
Monte Alto I
Onshore wind ยท Terra-Gen
142 MWAgreement signed Willacy, TXERCOT Nov 2016target 2028
Solar project J641, Morgan County
Solar
140 MWAgreement signed Morgan, ILMISO May 20162024
Vinton Solar
Solar
125 MWAgreement signed Vinton, OHPJM Oct 2016target 2027
Sycamore Creek Solar
Solar
117 MWAgreement signed Crawford, OHPJM Dec 2016target 2025
Mulqueeney Ranch Wind
Onshore wind
114 MWAgreement signed Alameda, CACAISO May 2016target 2026
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)