Onshore wind project GEN-2016-074, Custer County

Onshore wind project GEN-2016-074, Custer County is a 200 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Custer County, Nebraska, connecting to NPPD.

Queue statusConsented
  1. PlanningQueued Apr 2016 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2016-074
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Sweetwater 345kV
Location
Custer County, Nebraska
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
14 April 2016
Proposed online date
July 2027

Location

Marker shows the centre of Custer County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Custer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem