ONSHORE WIND Β· SPPOnshore wind project GEN-2017-001, Custer County
Onshore wind project GEN-2017-001, Custer County is a 250 MW onshore wind request withdrawn in the SPP interconnection queue, in Custer County, Nebraska, connecting to NPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2016 (completed)
- Withdrawn / abandonedDec 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2017-001
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- Sweetwater 345kV
- Location
- Custer County, Nebraska
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 December 2016
- Proposed online date
- December 2023
- Withdrawn
- December 2020
Location
Marker shows the centre of Custer County; the queue data does not give exact sites.
Other requests in Custer County
- Onshore wind project BHBE G13, Custer CountyOnshore wind Β· 300 MW Β· agreement signed
- Onshore wind project GEN-2016-074, Custer CountyOnshore wind Β· 200 MW Β· agreement signed
- Onshore wind project GEN-2006-038N005, Custer CountyOnshore wind Β· 80.0 MW Β· built
- Onshore wind project GEN-2006-037N1, Custer CountyOnshore wind Β· 75.0 MW Β· built
- Onshore wind project GEN-2023-133, Custer CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2024-233, Custer CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2016-026, Custer CountyOnshore wind Β· 120 MW Β· withdrawn
- Onshore wind project GEN-2006-038N006, Custer CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project GEN-2006-038N007, Custer CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project GEN-2016-025, Custer CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project GEN-2010-038, Custer CountyOnshore wind Β· 74.9 MW Β· withdrawn
- Onshore wind project GEN-2012-039, Custer CountyOnshore wind Β· 74.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem