United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Texas (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4910.1 GW
Active in queue10.1 GW49 requests
Agreement signed7,413 MW33 requests
Withdrawn9217.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

49 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Danish Fields Solar
Solar · Danish Fields Solar, LLC
603 MWAgreement signed Wharton, TXERCOT Apr 2018target 2026
Siete
Onshore wind · Apex Clean Energy
493 MWAgreement signed Webb, TXERCOT Oct 2018target 2028
Green Holly Solar
Solar · Copenhagen Infrastructure Partners Fund IV
414 MWPaused / redesign Dawson, TXERCOT Jul 2018target 2026
Baird North Wind
Onshore wind · BMP Wind, LLC
340 MWAgreement signed Callahan, TXERCOT May 2018target 2026
Quantum Solar
Solar + storage · IP QUANTUM II, LLC
322 MWAgreement signed Haskell, TXERCOT Sep 2018target 2026
Delilah Solar 2
Solar · Delilah Solar Energy II LLC
318 MWAgreement signed Lamar, TXERCOT Nov 2018target 2026
El Sauz Ranch
Onshore wind · El Sauz Ranch Wind, LLC
302 MWAgreement signed Willacy, TXERCOT Jun 2018target 2026
Pine Forest Solar
Solar · Pine Forest Solar I, LLC
302 MWAgreement signed Hopkins, TXERCOT Oct 2018target 2025
Delilah Solar 1
Solar · Delilah Solar Energy LLC
300 MWAgreement signed Lamar, TXERCOT Nov 2018target 2026
Arroyo Del Bisonte Solar
Solar · Sunchase Power
300 MWPaused / redesign Wharton, TXERCOT May 2018target 2021
Pierce Wind
Onshore wind
300 MWPaused / redesign Wharton, TXERCOT Jan 2018
Onshore wind project GEN-2018-099, Parmer County
Onshore wind
300 MWAgreement signed Parmer, TXSPP Nov 2018target 2027
Shifting Gale Wind
Onshore wind
289 MWPaused / redesign Castro, TXERCOT Apr 2018target 2025
Foxtrot Wind
Onshore wind · Lincoln Clean
268 MWAgreement signed Bee, TXERCOT Jul 2018target 2026
Red Holly Solar
Solar + storage · GreenGo Energy
260 MWAgreement signed Dawson, TXERCOT Jul 2018target 2027
Tulsita Solar
Solar · Ray Ranch Solar LLC
256 MWAgreement signed Goliad, TXERCOT Dec 2018target 2026
Maleza Solar
Solar + storage · Brush Solar LLC
255 MWAgreement signed Wharton, TXERCOT Dec 2018target 2027
Roseland Solar
Solar · Enel Green Power Roseland Solar, LLC
254 MWAgreement signed Falls, TXERCOT Nov 2018target 2025
Solar project GEN-2018-015, Cottle County
Solar
252 MWAgreement signed Cottle, TXSPP Apr 2018target 2027
Adamstown Solar
Solar · Adams Creek Solar Project, LLC
251 MWAgreement signed Wichita, TXERCOT Nov 2018target 2027
Samson Solar 1
Solar · Samson Solar Energy LLC
250 MWAgreement signed Lamar, TXERCOT Nov 2018target 2026
Eastbell Milam Solar
Solar · EDP RENEWABLES NORTH AMERICA LLC
245 MWAgreement signed Milam, TXERCOT Oct 2018target 2025
Peyton Creek Wind II
Onshore wind · RWE Renewables Development, LLC
241 MWAgreement signed Matagorda, TXERCOT Aug 2018target 2026
Gulf Wind 2
Onshore wind
227 MWPaused / redesign Kenedy, TXERCOT Jan 2018
Castro Solar
Solar · Castro Solar One, LLC
225 MWAgreement signed Castro, TXERCOT Feb 2018target 2028
Walleye Solar
Solar · Sandow Lakes Ranch Solar II, LLC
215 MWIn study Milam, TXERCOT Jul 2018target 2027
Diamondback solar
Solar · Diamondback Solar, LLC
204 MWAgreement signed Starr, TXERCOT Sep 2018target 2027
Rueter Solar
Solar
200 MWPaused / redesign Bosque, TXERCOT Sep 2018
Desert Rose Solar
Solar
200 MWPaused / redesign Andrews, TXERCOT Jun 2018
Onshore wind project GEN-2018-089, Castro County
Onshore wind
196 MWAgreement signed Castro, TXSPP Nov 2018target 2028
Fagus Solar Park 1 SLF
Solar + storage · Excel Advantage Services, LLC dba Misae Solar Park II
166 MWAgreement signed Childress, TXERCOT May 2018target 2026
CAROL wind
Onshore wind
165 MWPaused / redesign Potter, TXERCOT Dec 2018target 2024
Solar project GEN-2018-003, Bowie County
Solar
150 MWAgreement signed Bowie, TXSPP Apr 2018target 2027
Indigo Solar
Solar + storage · Innovative Solar 245, LLC
150 MWAgreement signed Fisher, TXERCOT Sep 2018target 2026
La Casa Wind
Onshore wind · LA CASA WIND, LLC
148 MWAgreement signed Stephens, TXERCOT Dec 2018target 2026
Wang Solar SLF
Solar + storage · BT Yixin Solar, LLC
145 MWIn study Falls, TXERCOT Jun 2018target 2026
Starr Solar Ranch
Solar + storage · Starr Solar Ranch 1 LLC
137 MWAgreement signed Starr, TXERCOT Nov 2018target 2025
Arroyo Solar
Solar + storage · BT Cantwell Solar, LLC
100 MWAgreement signed Cameron, TXERCOT May 2018target 2028
Tyson Nick Solar
Solar · Tyson Nick Solar Project, LLC
90.0 MWPaused / redesign Lamar, TXERCOT Dec 20182025
R Massengale
Gas
58.0 MWPaused / redesign Lubbock, TXERCOT Sep 2018target 2021
Red Holly Storage
Solar + storage · GreenGo Energy
50.0 MWAgreement signed Dawson, TXERCOT Sep 2018target 2028
Red Holly Storage 1
Solar + storage · GreenGo Energy
50.0 MWAgreement signed Dawson, TXERCOT Jul 2018target 2028
SP TX-12B Phase III
Solar · ConEd Development
40.0 MWIn study Upton, TXERCOT Sep 2018target 2025
Half Moon Battery
Battery storage
30.2 MWPaused / redesign Hidalgo, TXERCOT Sep 2018
Brandon
Gas
21.0 MWPaused / redesign Lubbock, TXERCOT Sep 2018target 2021
Air Products GCA
Gas · Air Products
14.0 MWAgreement signed Galveston, TXERCOT Jun 2018target 2025
Blue Summit repower
Onshore wind
9.9 MWPaused / redesign Wilbarger, TXERCOT Jan 2018
Indian Mesa repower
Onshore wind · Nextera
9.3 MWAgreement signed Pecos, TXERCOT May 2018target 2026
Sweetwater 1 repower
Onshore wind · Leeward Energy
3.0 MWAgreement signed Nolan, TXERCOT Feb 2018target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)