United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

SP TX-12B Phase III

SP TX-12B Phase III is a 40.0 MW solar request in interconnection study in the ERCOT interconnection queue, in Upton County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
19INR0189
Grid region
ERCOT (Texas)
Developer
ConEd Development
Connection point (POI)
76040 Castillo 138kV
Location
Upton County, Texas
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
12 September 2018
Proposed online date
December 2025

Location

Marker shows the centre of Upton County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Upton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem