United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESQueue requests in study in Texas (2022 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Southeast Oklahoma Pumped Storage Other · Apex Energy Solutions, LLC |
1,232 MW | In study |
| Shadow Ranch Solar Solar · LectricWind LLC |
808 MW | In study |
| Tempesta BESS Battery storage |
600 MW | Paused / redesign |
| Capoterra BESS Battery storage |
600 MW | Paused / redesign |
| Capoterra Solar |
598 MW | Paused / redesign |
| Brittlebush BESS Battery storage |
597 MW | Paused / redesign |
| Brittlebush Solar Solar |
594 MW | Paused / redesign |
| Point Mountain Solar Solar |
514 MW | Paused / redesign |
| Tres Rios Ranch Solar Solar + storage · LectricWind LLC |
508 MW | In study |
| Bayside BESS Battery storage |
508 MW | Paused / redesign |
| Hiru Storage Solar + storage · Hecate Energy Hazel LLC |
504 MW | In study |
| Hollow Branch Creek Storage Solar + storage · Hollow Branch Creek Solar LLC |
460 MW | In study |
| Tempesta Solar |
443 MW | Paused / redesign |
| Smith Lake Solar DC Solar + storage · Smith Lake Solar |
402 MW | In study |
| Bottom Grass Solar II Solar + storage · Flint Rock Solar Project, LLC |
402 MW | In study |
| Earthwise Solar Solar · Quanah Solar 2 |
371 MW | In study |
| Sombrero Solar Solar · Aurora Solar LLC |
352 MW | In study |
| HyFuels Green Lake Solar Solar · HyFuels Green Lake Solar LLC |
347 MW | In study |
| Royal River BESS Battery storage · Royal River LLC |
311 MW | In study |
| Glory Bee Solar Solar + storage · Riley Solar LLC |
305 MW | In study |
| Lake Henry Wind Onshore wind |
305 MW | Paused / redesign |
| Academy Wind Onshore wind |
305 MW | Paused / redesign |
| Furay Battery Energy Storage System Battery storage · Blue Topaz 1, LLC |
304 MW | In study |
| HyFuels Calhoun Solar Solar · HyFuels Green Lake Solar LLC |
302 MW | In study |
| Triangle Ranch Alpha Onshore wind · Triangle Ranch Wind |
302 MW | In study |
| Photo Solar 2 Solar + storage · CED Development Inc. |
300 MW | In study |
| Solar project J3045, Orange County Solar |
300 MW | In study |
| Camino Ranch Storage SLF Solar + storage · Camino Solar Ranch, LLC |
298 MW | In study |
| Camino Ranch Solar SLF Solar + storage · Camino Ranch Solar Project LLC |
296 MW | In study |
| Masava Storage Battery storage · Savannah Oaks Solar Project, LLC |
257 MW | In study |
| Bayside 2 BESS Battery storage |
252 MW | Paused / redesign |
| Best Southwest BESS Battery storage |
241 MW | Paused / redesign |
| Bora Bora Solar Solar |
233 MW | Paused / redesign |
| Petunia Storage Project Battery storage · Petunia Storage Project LLC |
232 MW | In study |
| Rubicon Echo Wind Onshore wind |
228 MW | Paused / redesign |
| White Tail Solar Solar · Mule Deer Solar LLC |
227 MW | In study |
| Dunkel BESS Battery storage · Momentum Energy Storage Partners |
226 MW | In study |
| Olympic BESS Battery storage · SMT Olympic BESS LLC |
223 MW | In study |
| Shoshana Storage Battery storage · Shoshana Storage Project LLC |
221 MW | In study |
| Sepanta Solar Solar · BREG - Belgian Renewable Energy Group |
217 MW | In study |
| Puerto Del Sol 2 Solar · PUERTO DEL SOL, LLC |
214 MW | In study |
| Puerto Del Sol 1 Solar · PUERTO DEL SOL, LLC |
214 MW | In study |
| Bessie Storage Battery storage · Bessie Energy Storage, LLC |
211 MW | In study |
| Forts Trail BESS Solar + storage · JC Central Bluff, LLC |
209 MW | In study |
| St. Gall Solar Solar · St. Gall Solar LLC |
207 MW | In study |
| Rock N' Roll Storage Two Solar + storage · Rock N‚Äô Roll Solar, LLC |
206 MW | In study |
| Soda Lake BESS 2 SLF Solar + storage · Crane II Solar Electric, LLC |
205 MW | In study |
| Citrus Grove Energy Storage Battery storage |
205 MW | Paused / redesign |
| Urca Solar Solar |
204 MW | Paused / redesign |
| Hoskins Solar Solar · SGT HOSKINS SOLAR PROJECT, LLC |
204 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)