United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTHoskins Solar
Hoskins Solar is a 204 MW solar request in interconnection study in the ERCOT interconnection queue, in Lamar County, Texas.
Queue statusIn planning
- PlanningQueued Oct 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0134
- Grid region
- ERCOT (Texas)
- Developer
- SGT HOSKINS SOLAR PROJECT, LLC
- Connection point (POI)
- TAP 138 kV 1687 BLOSSOM_T8 - 1771 LAMARBM1_8
- Location
- Lamar County, Texas
- Technology
- Solar: 204 MW
- Total requested
- 204 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 24 October 2022
- Proposed online date
- August 2026
Location
Marker shows the centre of Lamar County; the queue data does not give exact sites.
Other requests in Lamar County
- Baker Branch SolarSolar Β· 469 MW Β· agreement signed
- Bug Tussle Wind ProjectOnshore wind Β· 397 MW Β· agreement signed
- Rowdy Creek SolarSolar + storage Β· 352 MW Β· agreement signed
- Delilah Solar 2Solar Β· 318 MW Β· agreement signed
- Delilah Solar 1Solar Β· 300 MW Β· agreement signed
- Samson Solar 3Solar Β· 250 MW Β· agreement signed
- Samson Solar 1Solar Β· 250 MW Β· agreement signed
- Star Dairy StorageSolar + storage Β· 205 MW Β· agreement signed
- Samson Solar 2Solar Β· 203 MW Β· agreement signed
- Echols Grove, LLCSolar Β· 201 MW Β· agreement signed
- Rowdy Creek BESSSolar + storage Β· 176 MW Β· agreement signed
- MRG Goody SolarSolar + storage Β· 171 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem