United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Hoskins Solar

Hoskins Solar is a 204 MW solar request in interconnection study in the ERCOT interconnection queue, in Lamar County, Texas.

Queue statusIn planning
  1. PlanningQueued Oct 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0134
Grid region
ERCOT (Texas)
Developer
SGT HOSKINS SOLAR PROJECT, LLC
Connection point (POI)
TAP 138 kV 1687 BLOSSOM_T8 - 1771 LAMARBM1_8
Location
Lamar County, Texas
Technology
Solar: 204 MW
Total requested
204 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
24 October 2022
Proposed online date
August 2026

Location

Marker shows the centre of Lamar County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Lamar County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem