United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

BATTERY STORAGE Β· ERCOT

Bayside BESS

Bayside BESS is a 508 MW battery storage request suspended in the ERCOT interconnection queue, in Victoria County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0237
Grid region
ERCOT (Texas)
Location
Victoria County, Texas
Technology
Battery: 508 MW
Total requested
508 MW
Queue status
Suspended
Entered queue
6 March 2022

Location

Marker shows the centre of Victoria County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Victoria County