Hiru Storage

Hiru Storage is a 504 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Clay County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0444
Grid region
ERCOT (Texas)
Developer
Hecate Energy Hazel LLC
Connection point (POI)
Tap 345kV 6111 Riley - 1730 West Krum ckt 1
Location
Clay County, Texas
Technology
Battery: 504 MW · Battery
Total requested
504 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
15 November 2022
Proposed online date
April 2029

Location

Marker shows the centre of Clay County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Clay County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem