OCTARY USA ยท INTERCONNECTION QUEUES

Queue requests in study in Nebraska

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5611.4 GW
Active in queue16.5 GW85 requests
Agreement signed5,103 MW29 requests
Withdrawn25545.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

56 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-021, Lancaster County
Gas
540 MWIn study Lancaster, NESPP Oct 2024target 2030
Gas project GEN-2023-222, Gage County
Gas
478 MWIn study Gage, NESPP Oct 2023target 2030
Gas project GEN-2023-224, Lancaster County
Gas
478 MWIn study Lancaster, NESPP Oct 2023target 2029
Gas project GEN-2024-020, Lancaster County
Gas
390 MWIn study Lancaster, NESPP Oct 2024target 2030
Gas project GEN-2024-022, Gage County
Gas
390 MWIn study Gage, NESPP Oct 2024target 2030
Gas project GEN-2024-213, Cass County
Gas
360 MWIn study Cass, NESPP Mar 2025target 2035
Solar + storage project GEN-2020-011, Phelps County
Solar + storage
320 MWIn study Phelps, NESPP Apr 2020target 2028
Solar project GEN-2017-210, Cedar County
Solar
310 MWPaused / redesign Cedar, NESPP Nov 2017target 2026
Gas project GEN-2024-211, Cass County
Gas
303 MWIn study Cass, NESPP Mar 2025target 2035
Gas project GEN-2024-212, Cass County
Gas
303 MWIn study Cass, NESPP Mar 2025target 2035
Solar project GEN-2024-038, Nemaha County
Solar
300 MWIn study Nemaha, NESPP Oct 2024target 2029
Onshore wind project GEN-2021-057, Antelope County
Onshore wind
300 MWIn study Antelope, NESPP Apr 2021target 2027
Gas project GEN-2023-079, Cass County
Gas
273 MWIn study Cass, NESPP Oct 2023target 2032
Gas project GEN-2024-023, Gage County
Gas
270 MWIn study Gage, NESPP Oct 2024target 2030
Gas project GEN-2023-077, Cass County
Gas
255 MWIn study Cass, NESPP Oct 2023target 2028
Gas project GEN-2023-078, Cass County
Gas
255 MWIn study Cass, NESPP Oct 2023target 2028
Solar project GEN-2024-140, Douglas County
Solar
250 MWIn study Douglas, NESPP Mar 2025target 2033
Solar project GEN-2024-039, Nemaha County
Solar
250 MWIn study Nemaha, NESPP Oct 2024target 2029
Solar + storage project GEN-2023-199, Dakota County
Solar + storage
250 MWIn study Dakota, NESPP Oct 2023target 2027
Battery storage project GEN-2024-372, Douglas County
Battery storage
250 MWIn study Douglas, NESPP Mar 2025target 2028
Gas project GEN-2023-223, Gage County
Gas
239 MWIn study Gage, NESPP Oct 2023target 2030
Solar project GEN-2024-374, Scotts Bluff County
Solar
225 MWIn study Scotts Bluff, NESPP Mar 2025target 2030
Gas project GEN-2023-225, Lancaster County
Gas
217 MWIn study Lancaster, NESPP Oct 2023target 2029
Solar + storage project GEN-2020-013, Harlan County
Solar + storage
215 MWIn study Harlan, NESPP Apr 2020target 2027
Other project GEN-2025-SR24, Washington County
Other
200 MWIn study Washington, NESPP Jun 2025target 2028
Other project GEN-2025-SR26, Cass County
Other
200 MWIn study Cass, NESPP Jun 2025target 2029
Solar project GEN-2024-234, Burt County
Solar
200 MWIn study Burt, NESPP Mar 2025target 2029
Battery storage project GEN-2018-025, Washington County
Battery storage
200 MWPaused / redesign Washington, NESPP May 2018target 2028
Battery storage project GEN-2024-173, Lancaster County
Battery storage
200 MWIn study Lancaster, NESPP Mar 2025target 2028
Battery storage project GEN-2018-033, Cass County
Battery storage
200 MWPaused / redesign Cass, NESPP May 2018target 2029
Solar project GEN-2024-168, Fillmore County
Solar
200 MWIn study Fillmore, NESPP Mar 2025target 2033
Battery storage project GEN-2021-040, Cass County
Battery storage
200 MWIn study Cass, NESPP Apr 2021target 2029
Solar project GEN-2021-108, Cass County
Solar
182 MWIn study Cass, NESPP May 20212025
Solar project GEN-2024-040, Nemaha County
Solar
174 MWIn study Nemaha, NESPP Oct 2024target 2029
Battery storage project GEN-2024-051, Lancaster County
Battery storage
170 MWIn study Lancaster, NESPP Oct 2024target 2028
Battery storage project GEN-2025-SR31, Madison County
Battery storage
170 MWIn study Madison, NESPP Nov 2025target 2026
Battery storage project GEN-2024-065, Dodge County
Battery storage
150 MWIn study Dodge, NESPP Oct 2024target 2029
Battery storage project GEN-2023-SR7, Wayne County
Battery storage
135 MWIn study Wayne, NESPP Dec 20222024
Solar + storage project GEN-2023-153, Perkins County
Solar + storage
120 MWIn study Perkins, NESPP Oct 2023target 2028
Solar + storage project GEN-2024-162, Dakota County
Solar + storage
110 MWIn study Dakota, NESPP Mar 2025target 2030
Gas project ERAS-2025-001, Lancaster County
Gas
104 MWIn study Lancaster, NESPP Sep 2025target 2029
Solar project GEN-2021-027, Lancaster County
Solar
102 MWIn study Lancaster, NESPP May 2021target 2026
Solar project GEN-2019-009, Nemaha County
Solar
100 MWPaused / redesign Nemaha, NESPP Apr 2019target 2029
Battery storage project GEN-2021-039, Douglas County
Battery storage
100 MWIn study Douglas, NESPP Apr 2021target 2030
Other project GEN-2025-SR20, Douglas County
Other
100 MWIn study Douglas, NESPP Jun 2025target 2030
Battery storage project GEN-2018-037, Douglas County
Battery storage
100 MWPaused / redesign Douglas, NESPP May 2018target 2030
Battery storage project GEN-2024-SR10, Lancaster County
Battery storage
80.0 MWIn study Lancaster, NESPP Apr 2024target 2026
Solar project GEN-2019-041, Lancaster County
Solar
78.0 MWPaused / redesign Lancaster, NESPP May 2019target 2028
Battery storage project GEN-2024-SR8, Greeley County
Battery storage
70.0 MWIn study Greeley, NESPP Apr 2024target 2026
Other project GEN-2024-231, Richardson County
Other
65.0 MWIn study Richardson, NESPP Mar 2025target 2029
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)