Battery storage project J4072, Redwood County Battery storage |
500 MW | In study |
Redwood, MN | MISO |
Oct 2025 | target 2028 |
Battery storage project J4078, Mower County Battery storage |
500 MW | In study |
Mower, MN | MISO |
Oct 2025 | target 2030 |
Battery storage project J4194, Meeker County Battery storage |
500 MW | In study |
Meeker, MN | MISO |
Oct 2025 | target 2028 |
Battery storage project J4168, Goodhue County Battery storage |
330 MW | In study |
Goodhue, MN | MISO |
Oct 2025 | target 2028 |
Nobles BESS Battery storage Β· Xcel Energy |
314 MW | In study |
Nobles, MN | MISO |
Aug 2025 | target 2028 |
Sherco South BESS Battery storage Β· Xcel Energy |
314 MW | In study |
Sherburne, MN | MISO |
Aug 2025 | target 2027 |
Benton Energy Storage II Battery storage Β· Xcel Energy |
310 MW | In study |
Benton, MN | MISO |
Aug 2025 | target 2028 |
Battery storage project J2716, Dakota County Battery storage |
300 MW | In study |
Dakota, MN | MISO |
Sep 2022 | target 2027 |
Battery storage project J4089, Freeborn County Battery storage |
250 MW | In study |
Freeborn, MN | MISO |
Oct 2025 | target 2029 |
Battery storage project J3848, Wabasha County Battery storage |
250 MW | In study |
Wabasha, MN | MISO |
Dec 2024 | target 2030 |
Battery storage project J3894, Lyon County Battery storage |
250 MW | In study |
Lyon, MN | MISO |
Feb 2025 | target 2030 |
Battery storage project J3235, Benton County Battery storage |
250 MW | In study |
Benton, MN | MISO |
Mar 2024 | target 2028 |
Battery storage project J4117, Goodhue County Battery storage |
240 MW | In study |
Goodhue, MN | MISO |
Sep 2025 | target 2030 |
Sandhill Energy Storage Battery storage Β· Xcel Energy |
214 MW | In study |
Olmsted, MN | MISO |
Aug 2025 | target 2025 |
Battery storage project J3704, Redwood County Battery storage |
200 MW | In study |
Redwood, MN | MISO |
Apr 2024 | target 2028 |
Battery storage project J3236, Chisago County Battery storage |
200 MW | In study |
Chisago, MN | MISO |
Mar 2024 | target 2028 |
Battery storage project J2840, Olmsted County Battery storage |
200 MW | In study |
Olmsted, MN | MISO |
Sep 2022 | target 2025 |
Battery storage project J4065, Dakota County Battery storage |
200 MW | In study |
Dakota, MN | MISO |
Sep 2025 | target 2030 |
Surplus Battery storage |
200 MW | In study |
Nobles, MN | MISO |
Jan 2025 | target 2028 |
Battery storage project J3703, Itasca County Battery storage |
200 MW | In study |
Itasca, MN | MISO |
Mar 2024 | target 2028 |
Battery storage project J2601, Wabasha County Battery storage |
200 MW | In study |
Wabasha, MN | MISO |
Sep 2022 | target 2026 |
Battery storage project J1898, Olmsted County Battery storage |
200 MW | In study |
Olmsted, MN | MISO |
Aug 2021 | target 2024 |
Battery storage project J4087, Blue Earth County Battery storage |
183 MW | In study |
Blue Earth, MN | MISO |
Oct 2025 | target 2029 |
Battery storage project J3543, Dakota County Battery storage |
150 MW | In study |
Dakota, MN | MISO |
Apr 2024 | target 2028 |
Surplus; J1566 Battery storage |
150 MW | In study |
Martin, MN | MISO |
Jan 2025 | target 2028 |
Battery storage project J2731, Olmsted County Battery storage |
150 MW | In study |
Olmsted, MN | MISO |
Sep 2022 | target 2025 |
Battery storage project J2730, Jackson County Battery storage |
150 MW | In study |
Jackson, MN | MISO |
Sep 2022 | target 2025 |
Battery storage project J2728, Freeborn County Battery storage |
150 MW | In study |
Freeborn, MN | MISO |
Sep 2022 | target 2025 |
Surplus; J1426 Battery storage |
100 MW | In study |
Benton, MN | MISO |
Mar 2025 | target 2027 |
Battery storage project J3172, Dakota County Battery storage |
100 MW | In study |
Dakota, MN | MISO |
Sep 2022 | target 2026 |
Surplus; J385 Battery storage |
100 MW | In study |
Chisago, MN | MISO |
Aug 2025 | target 2027 |
Hoot Lake Battery Energy Storage System Battery storage Β· Otter Tail Power Company |
90.7 MW | In study |
Otter Tail, MN | MISO |
Aug 2025 | target 2028 |
Battery storage project J2879, Washington County Battery storage |
80.0 MW | In study |
Washington, MN | MISO |
Sep 2022 | target 2025 |
Battery storage project J2550, Yellow Medicine County Battery storage |
75.0 MW | In study |
Yellow Medicine, MN | MISO |
Sep 2022 | target 2030 |
Surplus; J1325 Battery storage |
72.0 MW | In study |
Rock, MN | MISO |
Feb 2025 | target 2027 |
Battery storage project J1045, Murray County Battery storage |
20.0 MW | Under construction |
Murray, MN | MISO |
Mar 2018 | target 2024 |