United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Minnesota (2024 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project J3547, Martin County Gas |
630 MW | Withdrawn / abandoned |
| Gas project J3549, Mower County Gas |
515 MW | Withdrawn / abandoned |
| Solar project J3823, Watonwan County Solar |
300 MW | Withdrawn / abandoned |
| Solar project J3524, Watonwan County Solar |
300 MW | Withdrawn / abandoned |
| Battery storage project J3259, Renville County Battery storage |
250 MW | Withdrawn / abandoned |
| Onshore wind project J3346, Lyon County Onshore wind |
250 MW | Withdrawn / abandoned |
| Solar project J3752, Aitkin County Solar |
220 MW | Withdrawn / abandoned |
| Battery storage project J3526, Goodhue County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project J3863, Itasca County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project J3705, Redwood County Onshore wind |
200 MW | Withdrawn / abandoned |
| Battery storage project J3369, Scott County Battery storage |
200 MW | Withdrawn / abandoned |
| Onshore wind project J3370, Kittson County Onshore wind |
150 MW | Withdrawn / abandoned |
| Battery storage project J3500, Chisago County Battery storage |
150 MW | Withdrawn / abandoned |
| Onshore wind project J3405, St. Louis County Onshore wind |
144 MW | Withdrawn / abandoned |
| Battery storage project J3234, Carver County Battery storage |
130 MW | Withdrawn / abandoned |
| Battery storage project J3312, Washington County Battery storage |
100 MW | Withdrawn / abandoned |
| Battery storage project J3665, Redwood County Battery storage |
100 MW | Withdrawn / abandoned |
| Battery storage project J3807, Goodhue County Battery storage |
100 MW | Withdrawn / abandoned |
| Battery storage project J3778, Otter Tail County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar project J3278, Swift County Solar |
90.0 MW | Withdrawn / abandoned |
| Onshore wind project J3237, Itasca County Onshore wind |
86.0 MW | Withdrawn / abandoned |
| Solar project J3397, Rock County Solar |
80.0 MW | Withdrawn / abandoned |
| Battery storage project J3791, Houston County Battery storage |
50.0 MW | Withdrawn / abandoned |
| Gas project J3445, Olmsted County Gas |
49.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)