Withdrawn queue requests in Minnesota (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown244,594 MW
Active in queue7,254 MW33 requests
Agreement signed0.0 MW0 requests
Withdrawn244,594 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J3547, Martin County
Gas
630 MWWithdrawn / abandoned Martin, MNMISO Apr 2024target 2026
Gas project J3549, Mower County
Gas
515 MWWithdrawn / abandoned Mower, MNMISO Apr 2024target 2026
Solar project J3823, Watonwan County
Solar
300 MWWithdrawn / abandoned Watonwan, MNMISO Apr 2024target 2028
Solar project J3524, Watonwan County
Solar
300 MWWithdrawn / abandoned Watonwan, MNMISO Apr 2024target 2028
Battery storage project J3259, Renville County
Battery storage
250 MWWithdrawn / abandoned Renville, MNMISO Apr 2024target 2028
Onshore wind project J3346, Lyon County
Onshore wind
250 MWWithdrawn / abandoned Lyon, MNMISO Apr 2024target 2028
Solar project J3752, Aitkin County
Solar
220 MWWithdrawn / abandoned Aitkin, MNMISO Apr 2024target 2028
Battery storage project J3526, Goodhue County
Battery storage
200 MWWithdrawn / abandoned Goodhue, MNMISO Apr 2024target 2030
Solar project J3863, Itasca County
Solar
200 MWWithdrawn / abandoned Itasca, MNMISO Dec 2024target 2028
Onshore wind project J3705, Redwood County
Onshore wind
200 MWWithdrawn / abandoned Redwood, MNMISO Apr 2024target 2028
Battery storage project J3369, Scott County
Battery storage
200 MWWithdrawn / abandoned Scott, MNMISO Mar 2024target 2028
Onshore wind project J3370, Kittson County
Onshore wind
150 MWWithdrawn / abandoned Kittson, MNMISO Apr 2024target 2028
Battery storage project J3500, Chisago County
Battery storage
150 MWWithdrawn / abandoned Chisago, MNMISO Apr 2024target 2028
Onshore wind project J3405, St. Louis County
Onshore wind
144 MWWithdrawn / abandoned St. Louis, MNMISO Apr 2024target 2028
Battery storage project J3234, Carver County
Battery storage
130 MWWithdrawn / abandoned Carver, MNMISO Mar 2024target 2028
Battery storage project J3312, Washington County
Battery storage
100 MWWithdrawn / abandoned Washington, MNMISO Apr 2024target 2028
Battery storage project J3665, Redwood County
Battery storage
100 MWWithdrawn / abandoned Redwood, MNMISO Apr 2024target 2028
Battery storage project J3807, Goodhue County
Battery storage
100 MWWithdrawn / abandoned Goodhue, MNMISO Apr 2024target 2028
Battery storage project J3778, Otter Tail County
Battery storage
100 MWWithdrawn / abandoned Otter Tail, MNMISO Apr 2024target 2028
Solar project J3278, Swift County
Solar
90.0 MWWithdrawn / abandoned Swift, MNMISO Apr 2024target 2028
Onshore wind project J3237, Itasca County
Onshore wind
86.0 MWWithdrawn / abandoned Itasca, MNMISO Apr 2024target 2028
Solar project J3397, Rock County
Solar
80.0 MWWithdrawn / abandoned Rock, MNMISO Mar 2024target 2026
Battery storage project J3791, Houston County
Battery storage
50.0 MWWithdrawn / abandoned Houston, MNMISO Apr 2024target 2028
Gas project J3445, Olmsted County
Gas
49.0 MWWithdrawn / abandoned Olmsted, MNMISO Apr 2024target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)