BATTERY STORAGE Β· MISOBattery storage project J3791, Houston County
Battery storage project J3791, Houston County is a 50.0 MW battery storage request withdrawn in the MISO interconnection queue, in Houston County, Minnesota, connecting to SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedSep 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3791
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY
- Connection point (POI)
- Caledonia
- Location
- Houston County, Minnesota
- Technology
- Battery: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 17 April 2024
- Proposed online date
- May 2028
- Withdrawn
- September 2025
Location
Marker shows the centre of Houston County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem