OCTARY USA ยท INTERCONNECTION QUEUES

Projects with signed interconnection agreements in West (non-ISO utilities)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown34960.6 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

349 requests ยท page 1 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q275, Navajo County
Solar + storage
1,000 MWAgreement signed Navajo, AZWest Mar 2018target 2020
Coal project GI-2003-3, Pueblo County
Coal
750 MWAgreement signed Pueblo, COWest Nov 2003target 2009
Solar + storage project Company LU, Mineral County
Solar + storage
700 MWAgreement signed Mineral, NVWest Sep 2021target 2029
Solar + storage project Company MI, Churchill County
Solar + storage
700 MWAgreement signed Churchill, NVWest Sep 2021target 2024
Gas project GI-2011-4, Denver County
Gas
687 MWAgreement signed Denver, COWest Apr 2011target 2015
Onshore wind project GI-2016-3, Lincoln County
Onshore wind
600 MWAgreement signed Lincoln, COWest Feb 2016target 2018
Other project Company KR, White Pine County
Other
600 MWAgreement signed White Pine, NVWest Sep 2020target 2028
Solar + storage project C2-45, Power County
Solar + storage ยท NextEra Energy Resources Interconnection Holdings, LLC
600 MWAgreement signed Power, IDWest Apr 2022target 2030
Solar project G0539, Deschutes County
Solar
600 MWAgreement signed Deschutes, ORWest May 2016target 2022
Onshore wind project 82, Meagher County
Onshore wind
600 MWAgreement signed Meagher, MTWest Feb 2019
Battery storage project 622, Malheur County
Battery storage ยท Owyhee Energy Storage, LLC
600 MWAgreement signed Malheur, ORWest Oct 2021target 2029
Solar + storage project Q360, Maricopa County
Solar + storage
550 MWAgreement signed Maricopa, AZWest Sep 2020target 2023
Solar + storage project 838, Utah County
Solar + storage ยท Faraday Interconnection LLC
525 MWAgreement signed Utah, UTWest Dec 2016target 2025
Battery storage project C2-10, Salt Lake County
Battery storage ยท Oquirrh Energy Storage, LLC
500 MWAgreement signed Salt Lake, UTWest Apr 2022target 2031
Onshore wind project C1-35, Carbon County
Onshore wind ยท Lucky Star Wind, LLC
500 MWAgreement signed Carbon, WYWest May 2021target 2028
Onshore wind project GI-2016-14, Cheyenne County
Onshore wind
500 MWAgreement signed Cheyenne, COWest Jul 20162020
Solar + storage project IA-PNM-2017-13, San Juan County
Solar + storage
500 MWAgreement signed San Juan, NMWest Oct 2017target 2020
Nuclear project C2-32, Lincoln County
Nuclear ยท US SFR Owner, LLC
500 MWAgreement signed Lincoln, WYWest Apr 2022target 2031
Solar + storage project IA-PNM-2019-11, San Juan County
Solar + storage ยท 450CT 8ME
500 MWAgreement signed San Juan, NMWest Apr 2019target 2025
Solar + storage project Company JK, Churchill County
Solar + storage
500 MWAgreement signed Churchill, NVWest Sep 2018target 2027
Gas project GI-2006-1e, El Paso County
Gas
483 MWAgreement signed El Paso, COWest Jan 2006target 2007
Coal project BHBE G11, Campbell County
Coal
475 MWAgreement signed Campbell, SDWest Sep 2011target 2011
Solar + storage project Q310, Yuma County
Solar + storage
450 MWAgreement signed Yuma, AZWest Aug 2019target 2023
Solar + storage project C1-11, Emery County
Solar + storage ยท Drunkards Wash Energy, LLC
450 MWAgreement signed Emery, UTWest Apr 2021target 2028
Onshore wind project IA-PNM-2016-02, Torrance Cty County
Onshore wind ยท Pacific Wind Development
402 MWAgreement signed Torrance Cty, NMWest May 2016target 2020
Onshore wind project GI-2006-1g, Logan County
Onshore wind
400 MWAgreement signed Logan, COWest Jan 2006target 2007
Solar + storage project Company KU, Lyon County
Solar + storage
400 MWAgreement signed Lyon, NVWest Sep 2020target 2025
Solar + storage project 787, Emery County
Solar + storage ยท Green River Solar I, LLC
400 MWAgreement signed Emery, UTWest Aug 2016target 2024
Solar + storage project Company MW, White Pine County
Solar + storage
400 MWAgreement signed White Pine, NVWest Mar 2022target 2030
Battery storage project 21-104, Washington County
Battery storage
400 MWAgreement signed Washington, ORWest Aug 2021target 2028
Solar + storage project Company 194, Clark County
Solar + storage
400 MWAgreement signed Clark, NVWest Mar 2021target 2023
Solar + storage project CLPT G21, Laramie County
Solar + storage
400 MWAgreement signed Laramie, WYWest Sep 2022target 2025
Solar + storage project Company LP, Lyon County
Solar + storage
400 MWAgreement signed Lyon, NVWest Sep 2021target 2029
Solar + storage project 665, Ada County
Solar + storage ยท Blacks Creek Energy Center, LLC
400 MWAgreement signed Ada, IDWest Aug 2022target 2027
Solar + storage project IA-PNM-2020-04, Bernalillo County
Solar + storage
400 MWAgreement signed Bernalillo, NMWest Jan 2020target 2023
Solar + storage project Company JI, Washoe County
Solar + storage
400 MWAgreement signed Washoe, NVWest Sep 2018target 2023
Onshore wind project GI-TC-2024-16, Laramie County
Onshore wind
400 MWAgreement signed Laramie, WYWest May 2023target 2029
Onshore wind project 836, Carbon County
Onshore wind ยท PacifiCorp
400 MWAgreement signed Carbon, WYWest Dec 2016target 2027
Solar + storage project GI-TC-2024-30, Morgan County
Solar + storage
400 MWAgreement signed Morgan, COWest May 2024target 2028
Solar + storage project GI-DISIS-2022-13, Prowers County
Solar + storage
398 MWAgreement signed Prowers, COWest May 2022target 2029
Gas project GI-2007-11, Weld County
Gas
380 MWAgreement signed Weld, COWest Oct 2007target 2009
Solar + storage project CLPT G20, Laramie County
Solar + storage
365 MWAgreement signed Laramie, WYWest Jul 2022target 2025
Solar project Company IF, Humboldt County
Solar
350 MWAgreement signed Humboldt, NVWest Mar 2018target 2026
Battery storage project Company 242, Clark County
Battery storage
350 MWAgreement signed Clark, NVWest Mar 2023target 2028
Other project 590, Elmore County
Other ยท Appaloosa Wind And Solar LLC
330 MWAgreement signed Elmore, IDWest Dec 2020target 2027
Battery storage project 696, Owyhee County
Battery storage ยท KCE ID 1, LLC
330 MWAgreement signed Owyhee, IDWest Dec 2022target 2026
Onshore wind project 83, Meagher County
Onshore wind
300 MWAgreement signed Meagher, MTWest Mar 2019
Solar + storage project Company MB, White Pine County
Solar + storage
300 MWAgreement signed White Pine, NVWest Sep 2021target 2028
Onshore wind project GI-2006-1i, Weld County
Onshore wind
300 MWAgreement signed Weld, COWest Jan 2006target 2007
Other project CLPT G17, Laramie County
Other ยท NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Laramie, WYWest Apr 2022target 2025
Page 1 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)