United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESProjects with signed interconnection agreements in West (non-ISO utilities)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project Q275, Navajo County Solar + storage |
1,000 MW | Agreement signed |
| Coal project GI-2003-3, Pueblo County Coal |
750 MW | Agreement signed |
| Solar + storage project Company LU, Mineral County Solar + storage |
700 MW | Agreement signed |
| Solar + storage project Company MI, Churchill County Solar + storage |
700 MW | Agreement signed |
| Gas project GI-2011-4, Denver County Gas |
687 MW | Agreement signed |
| Onshore wind project GI-2016-3, Lincoln County Onshore wind |
600 MW | Agreement signed |
| Other project Company KR, White Pine County Other |
600 MW | Agreement signed |
| Solar + storage project C2-45, Power County Solar + storage ยท NextEra Energy Resources Interconnection Holdings, LLC |
600 MW | Agreement signed |
| Solar project G0539, Deschutes County Solar |
600 MW | Agreement signed |
| Onshore wind project 82, Meagher County Onshore wind |
600 MW | Agreement signed |
| Battery storage project 622, Malheur County Battery storage ยท Owyhee Energy Storage, LLC |
600 MW | Agreement signed |
| Solar + storage project Q360, Maricopa County Solar + storage |
550 MW | Agreement signed |
| Solar + storage project 838, Utah County Solar + storage ยท Faraday Interconnection LLC |
525 MW | Agreement signed |
| Battery storage project C2-10, Salt Lake County Battery storage ยท Oquirrh Energy Storage, LLC |
500 MW | Agreement signed |
| Onshore wind project C1-35, Carbon County Onshore wind ยท Lucky Star Wind, LLC |
500 MW | Agreement signed |
| Onshore wind project GI-2016-14, Cheyenne County Onshore wind |
500 MW | Agreement signed |
| Solar + storage project IA-PNM-2017-13, San Juan County Solar + storage |
500 MW | Agreement signed |
| Nuclear project C2-32, Lincoln County Nuclear ยท US SFR Owner, LLC |
500 MW | Agreement signed |
| Solar + storage project IA-PNM-2019-11, San Juan County Solar + storage ยท 450CT 8ME |
500 MW | Agreement signed |
| Solar + storage project Company JK, Churchill County Solar + storage |
500 MW | Agreement signed |
| Gas project GI-2006-1e, El Paso County Gas |
483 MW | Agreement signed |
| Coal project BHBE G11, Campbell County Coal |
475 MW | Agreement signed |
| Solar + storage project Q310, Yuma County Solar + storage |
450 MW | Agreement signed |
| Solar + storage project C1-11, Emery County Solar + storage ยท Drunkards Wash Energy, LLC |
450 MW | Agreement signed |
| Onshore wind project IA-PNM-2016-02, Torrance Cty County Onshore wind ยท Pacific Wind Development |
402 MW | Agreement signed |
| Onshore wind project GI-2006-1g, Logan County Onshore wind |
400 MW | Agreement signed |
| Solar + storage project Company KU, Lyon County Solar + storage |
400 MW | Agreement signed |
| Solar + storage project 787, Emery County Solar + storage ยท Green River Solar I, LLC |
400 MW | Agreement signed |
| Solar + storage project Company MW, White Pine County Solar + storage |
400 MW | Agreement signed |
| Battery storage project 21-104, Washington County Battery storage |
400 MW | Agreement signed |
| Solar + storage project Company 194, Clark County Solar + storage |
400 MW | Agreement signed |
| Solar + storage project CLPT G21, Laramie County Solar + storage |
400 MW | Agreement signed |
| Solar + storage project Company LP, Lyon County Solar + storage |
400 MW | Agreement signed |
| Solar + storage project 665, Ada County Solar + storage ยท Blacks Creek Energy Center, LLC |
400 MW | Agreement signed |
| Solar + storage project IA-PNM-2020-04, Bernalillo County Solar + storage |
400 MW | Agreement signed |
| Solar + storage project Company JI, Washoe County Solar + storage |
400 MW | Agreement signed |
| Onshore wind project GI-TC-2024-16, Laramie County Onshore wind |
400 MW | Agreement signed |
| Onshore wind project 836, Carbon County Onshore wind ยท PacifiCorp |
400 MW | Agreement signed |
| Solar + storage project GI-TC-2024-30, Morgan County Solar + storage |
400 MW | Agreement signed |
| Solar + storage project GI-DISIS-2022-13, Prowers County Solar + storage |
398 MW | Agreement signed |
| Gas project GI-2007-11, Weld County Gas |
380 MW | Agreement signed |
| Solar + storage project CLPT G20, Laramie County Solar + storage |
365 MW | Agreement signed |
| Solar project Company IF, Humboldt County Solar |
350 MW | Agreement signed |
| Battery storage project Company 242, Clark County Battery storage |
350 MW | Agreement signed |
| Other project 590, Elmore County Other ยท Appaloosa Wind And Solar LLC |
330 MW | Agreement signed |
| Battery storage project 696, Owyhee County Battery storage ยท KCE ID 1, LLC |
330 MW | Agreement signed |
| Onshore wind project 83, Meagher County Onshore wind |
300 MW | Agreement signed |
| Solar + storage project Company MB, White Pine County Solar + storage |
300 MW | Agreement signed |
| Onshore wind project GI-2006-1i, Weld County Onshore wind |
300 MW | Agreement signed |
| Other project CLPT G17, Laramie County Other ยท NextEra Energy Resources Interconnection Holdings, LLC |
300 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)578 ยท 119.3 GW
- CAISO (California)235 ยท 96.2 GW
- West (non-ISO utilities)349 ยท 60.6 GW
- Southeast (non-ISO utilities)192 ยท 37.8 GW
- SPP (Southwest Power Pool)212 ยท 37.6 GW
- PJM (Mid-Atlantic, Midwest)343 ยท 35.0 GW
- MISO (Midcontinent)187 ยท 28.1 GW
- ISO-NE (New England)45 ยท 8,609 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)