Projects with signed interconnection agreements in SPP (Southwest Power Pool)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown21237.6 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

212 requests Β· page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2020-065, Gaines County
Gas
1,003 MWAgreement signed Gaines, NMSPP Apr 2020target 2028
Solar + storage project GEN-2020-007, Linn County
Solar + storage
650 MWAgreement signed Linn, KSSPP Apr 2020target 2028
Onshore wind project GEN-2016-119, Kingfisher County
Onshore wind
600 MWAgreement signed Kingfisher, OKSPP Nov 20162025
Gas project GEN-2024-GR5, Chouteau County
Gas
594 MWAgreement signed Chouteau, OKSPP Aug 2024target 2026
Gas project GEN-2022-GR1, Harrison County
Gas
513 MWAgreement signed Harrison, TXSPP Mar 2022target 2027
Solar project GEN-2017-195, Johnson County
Solar
500 MWAgreement signed Johnson, KSSPP Nov 2017target 2030
Solar project GEN-2018-043, Burt County
Solar
500 MWAgreement signed Burt, NESPP May 2018target 2028
Gas project GEN-2024-GR1, Oklahoma County
Gas
492 MWAgreement signed Oklahoma, OKSPP Jan 2024target 2026
Battery storage project GEN-2020-057, Finney County
Battery storage
425 MWAgreement signed Finney, KSSPP Apr 2020target 2030
Solar project GEN-2020-058, Finney County
Solar
425 MWAgreement signed Finney, KSSPP Apr 2020target 2028
Onshore wind project GEN-2017-183, Hodgeman County
Onshore wind
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Solar project GEN-2017-108, Henry County
Solar
400 MWAgreement signed Henry, MOSPP Aug 2017target 2027
Solar project GEN-2017-184, Hodgeman County
Solar
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Onshore wind project GEN-2016-141, Texas County
Onshore wind
350 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Battery storage project GEN-2021-005, Saline County
Battery storage
350 MWAgreement signed Saline, KSSPP May 2021target 2030
Onshore wind project GEN-2016-142, Texas County
Onshore wind
350 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Solar project GEN-2020-084, Burt County
Solar
350 MWAgreement signed Burt, NESPP Apr 2020target 2030
Solar project GEN-2021-023, Grant County
Solar
306 MWAgreement signed Grant, KSSPP May 2021target 2030
Onshore wind project GEN-2016-111, Mcpherson County
Onshore wind
302 MWAgreement signed Mcpherson, KSSPP Nov 2016target 2027
Solar project GEN-2017-239, Yoakum County
Solar
300 MWAgreement signed Yoakum, TXSPP Nov 2017target 2026
Solar project GEN-2021-053, Muskogee County
Solar
300 MWAgreement signed Muskogee, OKSPP Apr 2021target 2031
Solar project GEN-2018-048, Caddo County
Solar
300 MWAgreement signed Caddo, OKSPP May 2018target 2028
Onshore wind project GEN-2017-014, Haakon County
Onshore wind
300 MWAgreement signed Haakon, SDSPP May 2017target 2027
Onshore wind project GEN-2021-056, Harper County
Onshore wind
300 MWAgreement signed Harper, KSSPP Apr 2021target 2030
Onshore wind project GEN-2017-151, Crosby County
Onshore wind
300 MWAgreement signed Crosby, TXSPP Nov 2017target 2026
Onshore wind project GEN-2018-099, Parmer County
Onshore wind
300 MWAgreement signed Parmer, TXSPP Nov 2018target 2027
Onshore wind project GEN-2017-181, Lancaster County
Onshore wind
300 MWAgreement signed Lancaster, NESPP Nov 2017target 2028
Solar project GEN-2020-054, Bowie County
Solar
298 MWAgreement signed Bowie, TXSPP Apr 2020target 2027
Onshore wind project GEN-2017-137, Oklahoma County
Onshore wind
295 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Gas project GEN-2020-038, Cass County
Gas
273 MWAgreement signed Cass, NESPP Apr 2020target 2028
Gas project GEN-2020-031, Sarpy County
Gas
273 MWAgreement signed Sarpy, NESPP Apr 2020target 2028
Onshore wind project GEN-2017-175, Turner County
Onshore wind
270 MWAgreement signed Turner, SDSPP Nov 2017target 2028
Onshore wind project GEN-2017-158, Parmer County
Onshore wind
265 MWAgreement signed Parmer, TXSPP Nov 2017target 2026
Onshore wind project GEN-2017-120, Dickinson County
Onshore wind
260 MWAgreement signed Dickinson, KSSPP Nov 2017target 2028
Onshore wind project GEN-2017-149, Johnston County
Onshore wind
258 MWAgreement signed Johnston, OKSPP Nov 2017target 2027
Onshore wind project GEN-2018-067, Williams County
Onshore wind
255 MWAgreement signed Williams, NDSPP Oct 2018target 2028
Onshore wind project GEN-2019-030, Ford County
Onshore wind
252 MWAgreement signed Ford, KSSPP Apr 2019target 2027
Solar project GEN-2018-055, Grady County
Solar
252 MWAgreement signed Grady, OKSPP May 2018target 2026
Solar project GEN-2018-015, Cottle County
Solar
252 MWAgreement signed Cottle, TXSPP Apr 2018target 2027
Solar + storage project GEN-2020-008, Stevens County
Solar + storage
250 MWAgreement signed Stevens, KSSPP Apr 2020target 2028
Battery storage project GEN-2021-043, Lancaster County
Battery storage
250 MWAgreement signed Lancaster, NESPP Apr 2021target 2030
Solar project GEN-2017-150, Grady County
Solar
250 MWAgreement signed Grady, OKSPP Nov 2017target 2026
Solar project GEN-2017-164, Garfield County
Solar
250 MWAgreement signed Garfield, OKSPP Nov 20172025
Solar project GEN-2021-047, Mayes County
Solar
250 MWAgreement signed Mayes, OKSPP Apr 2021target 2029
Onshore wind project GEN-2017-134, Oklahoma County
Onshore wind
250 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Solar project GEN-2020-094, Otoe County
Solar
250 MWAgreement signed Otoe, NESPP Apr 2020target 2030
Solar + storage project GEN-2018-115, Comanche County
Solar + storage
250 MWAgreement signed Comanche, OKSPP Nov 2018target 2029
Onshore wind project GEN-2017-201, Wayne County
Onshore wind
250 MWAgreement signed Wayne, NESPP Nov 2017target 2028
Solar project GEN-2017-141, Wagoner County
Solar
242 MWAgreement signed Wagoner, OKSPP Nov 2017target 2027
Solar project GEN-2021-018, Noble County
Solar
231 MWAgreement signed Noble, OKSPP Apr 2021target 2028
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)