Gas project GEN-2020-065, Gaines County Gas |
1,003 MW | Agreement signed |
Gaines, NM | SPP |
Apr 2020 | target 2028 |
Solar + storage project GEN-2020-007, Linn County Solar + storage |
650 MW | Agreement signed |
Linn, KS | SPP |
Apr 2020 | target 2028 |
Onshore wind project GEN-2016-119, Kingfisher County Onshore wind |
600 MW | Agreement signed |
Kingfisher, OK | SPP |
Nov 2016 | 2025 |
Gas project GEN-2024-GR5, Chouteau County Gas |
594 MW | Agreement signed |
Chouteau, OK | SPP |
Aug 2024 | target 2026 |
Gas project GEN-2022-GR1, Harrison County Gas |
513 MW | Agreement signed |
Harrison, TX | SPP |
Mar 2022 | target 2027 |
Solar project GEN-2017-195, Johnson County Solar |
500 MW | Agreement signed |
Johnson, KS | SPP |
Nov 2017 | target 2030 |
Solar project GEN-2018-043, Burt County Solar |
500 MW | Agreement signed |
Burt, NE | SPP |
May 2018 | target 2028 |
Gas project GEN-2024-GR1, Oklahoma County Gas |
492 MW | Agreement signed |
Oklahoma, OK | SPP |
Jan 2024 | target 2026 |
Battery storage project GEN-2020-057, Finney County Battery storage |
425 MW | Agreement signed |
Finney, KS | SPP |
Apr 2020 | target 2030 |
Solar project GEN-2020-058, Finney County Solar |
425 MW | Agreement signed |
Finney, KS | SPP |
Apr 2020 | target 2028 |
Onshore wind project GEN-2017-183, Hodgeman County Onshore wind |
400 MW | Agreement signed |
Hodgeman, KS | SPP |
Nov 2017 | target 2029 |
Solar project GEN-2017-108, Henry County Solar |
400 MW | Agreement signed |
Henry, MO | SPP |
Aug 2017 | target 2027 |
Solar project GEN-2017-184, Hodgeman County Solar |
400 MW | Agreement signed |
Hodgeman, KS | SPP |
Nov 2017 | target 2029 |
Onshore wind project GEN-2016-141, Texas County Onshore wind |
350 MW | Agreement signed |
Texas, OK | SPP |
Nov 2016 | target 2029 |
Battery storage project GEN-2021-005, Saline County Battery storage |
350 MW | Agreement signed |
Saline, KS | SPP |
May 2021 | target 2030 |
Onshore wind project GEN-2016-142, Texas County Onshore wind |
350 MW | Agreement signed |
Texas, OK | SPP |
Nov 2016 | target 2029 |
Solar project GEN-2020-084, Burt County Solar |
350 MW | Agreement signed |
Burt, NE | SPP |
Apr 2020 | target 2030 |
Solar project GEN-2021-023, Grant County Solar |
306 MW | Agreement signed |
Grant, KS | SPP |
May 2021 | target 2030 |
Onshore wind project GEN-2016-111, Mcpherson County Onshore wind |
302 MW | Agreement signed |
Mcpherson, KS | SPP |
Nov 2016 | target 2027 |
Solar project GEN-2017-239, Yoakum County Solar |
300 MW | Agreement signed |
Yoakum, TX | SPP |
Nov 2017 | target 2026 |
Solar project GEN-2021-053, Muskogee County Solar |
300 MW | Agreement signed |
Muskogee, OK | SPP |
Apr 2021 | target 2031 |
Solar project GEN-2018-048, Caddo County Solar |
300 MW | Agreement signed |
Caddo, OK | SPP |
May 2018 | target 2028 |
Onshore wind project GEN-2017-014, Haakon County Onshore wind |
300 MW | Agreement signed |
Haakon, SD | SPP |
May 2017 | target 2027 |
Onshore wind project GEN-2021-056, Harper County Onshore wind |
300 MW | Agreement signed |
Harper, KS | SPP |
Apr 2021 | target 2030 |
Onshore wind project GEN-2017-151, Crosby County Onshore wind |
300 MW | Agreement signed |
Crosby, TX | SPP |
Nov 2017 | target 2026 |
Onshore wind project GEN-2018-099, Parmer County Onshore wind |
300 MW | Agreement signed |
Parmer, TX | SPP |
Nov 2018 | target 2027 |
Onshore wind project GEN-2017-181, Lancaster County Onshore wind |
300 MW | Agreement signed |
Lancaster, NE | SPP |
Nov 2017 | target 2028 |
Solar project GEN-2020-054, Bowie County Solar |
298 MW | Agreement signed |
Bowie, TX | SPP |
Apr 2020 | target 2027 |
Onshore wind project GEN-2017-137, Oklahoma County Onshore wind |
295 MW | Agreement signed |
Oklahoma, OK | SPP |
Nov 2017 | target 2030 |
Gas project GEN-2020-038, Cass County Gas |
273 MW | Agreement signed |
Cass, NE | SPP |
Apr 2020 | target 2028 |
Gas project GEN-2020-031, Sarpy County Gas |
273 MW | Agreement signed |
Sarpy, NE | SPP |
Apr 2020 | target 2028 |
Onshore wind project GEN-2017-175, Turner County Onshore wind |
270 MW | Agreement signed |
Turner, SD | SPP |
Nov 2017 | target 2028 |
Onshore wind project GEN-2017-158, Parmer County Onshore wind |
265 MW | Agreement signed |
Parmer, TX | SPP |
Nov 2017 | target 2026 |
Onshore wind project GEN-2017-120, Dickinson County Onshore wind |
260 MW | Agreement signed |
Dickinson, KS | SPP |
Nov 2017 | target 2028 |
Onshore wind project GEN-2017-149, Johnston County Onshore wind |
258 MW | Agreement signed |
Johnston, OK | SPP |
Nov 2017 | target 2027 |
Onshore wind project GEN-2018-067, Williams County Onshore wind |
255 MW | Agreement signed |
Williams, ND | SPP |
Oct 2018 | target 2028 |
Onshore wind project GEN-2019-030, Ford County Onshore wind |
252 MW | Agreement signed |
Ford, KS | SPP |
Apr 2019 | target 2027 |
Solar project GEN-2018-055, Grady County Solar |
252 MW | Agreement signed |
Grady, OK | SPP |
May 2018 | target 2026 |
Solar project GEN-2018-015, Cottle County Solar |
252 MW | Agreement signed |
Cottle, TX | SPP |
Apr 2018 | target 2027 |
Solar + storage project GEN-2020-008, Stevens County Solar + storage |
250 MW | Agreement signed |
Stevens, KS | SPP |
Apr 2020 | target 2028 |
Battery storage project GEN-2021-043, Lancaster County Battery storage |
250 MW | Agreement signed |
Lancaster, NE | SPP |
Apr 2021 | target 2030 |
Solar project GEN-2017-150, Grady County Solar |
250 MW | Agreement signed |
Grady, OK | SPP |
Nov 2017 | target 2026 |
Solar project GEN-2017-164, Garfield County Solar |
250 MW | Agreement signed |
Garfield, OK | SPP |
Nov 2017 | 2025 |
Solar project GEN-2021-047, Mayes County Solar |
250 MW | Agreement signed |
Mayes, OK | SPP |
Apr 2021 | target 2029 |
Onshore wind project GEN-2017-134, Oklahoma County Onshore wind |
250 MW | Agreement signed |
Oklahoma, OK | SPP |
Nov 2017 | target 2030 |
Solar project GEN-2020-094, Otoe County Solar |
250 MW | Agreement signed |
Otoe, NE | SPP |
Apr 2020 | target 2030 |
Solar + storage project GEN-2018-115, Comanche County Solar + storage |
250 MW | Agreement signed |
Comanche, OK | SPP |
Nov 2018 | target 2029 |
Onshore wind project GEN-2017-201, Wayne County Onshore wind |
250 MW | Agreement signed |
Wayne, NE | SPP |
Nov 2017 | target 2028 |
Solar project GEN-2017-141, Wagoner County Solar |
242 MW | Agreement signed |
Wagoner, OK | SPP |
Nov 2017 | target 2027 |
Solar project GEN-2021-018, Noble County Solar |
231 MW | Agreement signed |
Noble, OK | SPP |
Apr 2021 | target 2028 |