United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in North Dakota, MISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown316,519 MW
Active in queue6,519 MW31 requests
Agreement signed1,001 MW5 requests
Withdrawn17430.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

31 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J4105, Cass County
Solar + storage
500 MWIn study Cass, NDMISO Oct 2025target 2028
Solar + storage project J4106, Cass County
Solar + storage
500 MWIn study Cass, NDMISO Oct 2025target 2027
Other project J3163, Cass County
Other
479 MWIn study Cass, NDMISO Jul 2022target 2028
Red Butte Wind
Onshore wind Β· Red Butte Wind, LLC
457 MWIn study Morton, NDMISO Aug 2025target 2028
Onshore wind project MPC04000, Oliver County
Onshore wind
300 MWAgreement signed Oliver, NDMISO Apr 2019target 2023
Onshore wind project J3280, Dickey County
Onshore wind
300 MWIn study Dickey, NDMISO Apr 2024target 2028
Onshore wind project MPC04500, Grand Forks County
Onshore wind
258 MWIn study Grand Forks, NDMISO Sep 2023target 2028
Onshore wind project MPC03800, Eddy County
Onshore wind
250 MWAgreement signed Eddy, NDMISO Feb 2019target 2027
Onshore wind project J1040, Mcintosh County
Onshore wind
250 MWUnder construction Mcintosh, NDMISO Mar 2018target 2023
Solar project J3787, Stutsman County
Solar
247 MWIn study Stutsman, NDMISO Apr 2024target 2028
Battery storage project MPC04600, Eddy County
Battery storage
209 MWIn study Eddy, NDMISO Nov 2025target 2028
Onshore wind project MPC04400, Grand Forks County
Onshore wind
206 MWIn study Grand Forks, NDMISO Feb 2022target 2024
Onshore wind project J2080, Oliver County
Onshore wind
200 MWIn study Oliver, NDMISO Aug 2021target 2024
Onshore wind project J2250, Stutsman County
Onshore wind
200 MWIn study Stutsman, NDMISO Nov 2021target 2024
Solar project J1588, Cass County
Solar
200 MWIn study Cass, NDMISO Apr 2024target 2026
Solar project J3522, Cass County
Solar
200 MWIn study Cass, NDMISO Mar 2024target 2028
Onshore wind project J3833, Cass County
Onshore wind
200 MWIn study Cass, NDMISO Oct 2024target 2028
Surplus; J1588
Battery storage
200 MWIn study Cass, NDMISO Mar 2025target 2028
Solar + storage project J4170, Richland County
Solar + storage
172 MWIn study Richland, NDMISO Oct 2025target 2029
Solar project MPC03600, Richland County
Solar
170 MWAgreement signed Richland, NDMISO May 2018target 2027
Onshore wind project MPC03900, Eddy County
Onshore wind
151 MWAgreement signed Eddy, NDMISO Apr 2019target 2027
Onshore wind project J2502, Morton County
Onshore wind
150 MWIn study Morton, NDMISO Sep 2022target 2025
Solar project MPC03700, Richland County
Solar
130 MWAgreement signed Richland, NDMISO May 2018target 2027
Replace 103.1 MW of Heskett Units 1 & 2 with One (1) General Electric synchronous combustion turbine; Heskett 1 & 2
Gas
103 MWIn study Morton, NDMISO Jun 20192024
Onshore wind project J2157, Morton County
Onshore wind
100 MWIn study Morton, NDMISO Aug 2021target 2025
Onshore wind project J3070, Morton County
Onshore wind
100 MWIn study Morton, NDMISO Sep 2022target 2025
Onshore wind project J2097, Morton County
Onshore wind
100 MWIn study Morton, NDMISO Aug 2021target 2025
Battery storage project J2913, Sargent County
Battery storage
90.0 MWIn study Sargent, NDMISO Sep 2022target 2025
Solar project J4077, Emmons County
Solar
45.0 MWIn study Emmons, NDMISO Oct 2025target 2030
Solar project J4070, Emmons County
Solar
40.0 MWIn study Emmons, NDMISO Oct 2025target 2030
Other project G150, Mcintosh County
Other
12.0 MWIn study Mcintosh, NDMISO Nov 2001target 2002

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)