Solar project MPC03700, Richland County is a 130 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Richland County, North Dakota, connecting to Minnkota Power Cooperative.

Queue statusConsented
  1. PlanningQueued May 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
MPC03700
Grid region
MISO (Midcontinent)
Utility / transmission owner
Minnkota Power Cooperative
Connection point (POI)
Frontier-Wahpeton 230 kV Line
Location
Richland County, North Dakota
Technology
Solar: 130 MW
Total requested
130 MW
Service type
Energy only (ERIS)
Study phase
GIA Executed
Queue status
Active
Entered queue
4 May 2018
Proposed online date
April 2027

Location

Marker shows the centre of Richland County; the queue data does not give exact sites.