United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Battery storage interconnection queue in ERCOT (Texas)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown724133.4 GW
Active in queue133.4 GW724 requests
Agreement signed26.6 GW178 requests
Withdrawn14224.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

724 requests · page 1 of 15
ProjectCapacityStatusLocationRegionQueuedOnline
Kickstart Energy Storage VI
Battery storage · Kickstart Infrastructure LLC
1,026 MWIn study Ellis, TXERCOT Dec 2025target 2029
Kickstart Energy Storage V
Battery storage · Kickstart Infrastructure LLC
999 MWIn study Ellis, TXERCOT Nov 2025target 2029
Nabla Energy Storage I
Battery storage · Nabla Park LLC
750 MWIn study Tarrant, TXERCOT Nov 2025target 2028
Nabla Energy Storage II
Battery storage · Nabla Park LLC
750 MWIn study Parker, TXERCOT Nov 2025target 2028
Howard Road BESS
Battery storage · Project Fast Flow LLC
618 MWIn study Bexar, TXERCOT Jul 2025target 2028
Comanche BESS
Battery storage · ENERGOS BESS
614 MWIn study Comanche, TXERCOT Dec 2024target 2028
Symphony BESS
Battery storage · Symphony BESS, LLC
612 MWIn study Austin, TXERCOT Feb 2025target 2028
Lavita BESS
Battery storage · Lavita BESS, LLC
606 MWIn study Bell, TXERCOT Dec 2024target 2028
Hobby BESS I
Battery storage · Airport Storage II LLC
603 MWIn study Harris, TXERCOT Sep 2024target 2027
Tempesta BESS
Battery storage
600 MWPaused / redesign Kaufman, TXERCOT Jun 2022
Capoterra BESS
Battery storage
600 MWPaused / redesign Milam, TXERCOT Jun 2022
Brittlebush BESS
Battery storage
597 MWPaused / redesign Henderson, TXERCOT Jun 2022
Toce TX BESS 2
Battery storage · TOCE TX BESS 2, LLC
523 MWIn study Wharton, TXERCOT Feb 2024target 2027
Knight Airport BESS I
Battery storage · Airport Storage I LLC
523 MWIn study Harris, TXERCOT Aug 2024target 2027
Avalon BESS
Battery storage · Avalon BESS, LLC
522 MWAgreement signed Fort Bend, TXERCOT Dec 2023target 2026
Falcon BESS
Battery storage · Falcon Energy Project, LLC
517 MWIn study Zapata, TXERCOT Sep 2025target 2028
Ochoa Energy Storage II
Battery storage · Ochoa Energy Storage II LLC
517 MWIn study Waller, TXERCOT Apr 2024target 2029
Catamount Storage
Battery storage · TOCE TX BESS 3, LLC
515 MWIn study Harris, TXERCOT Sep 2024target 2028
Seven Angels Energy Storage II
Battery storage · Seven Angels Infrastructure LLC
514 MWIn study Hill, TXERCOT Nov 2025target 2028
Seven Angels Energy Storage I
Battery storage · Seven Angels Infrastructure LLC
514 MWIn study Hill, TXERCOT Nov 2025target 2028
Diamante BESS
Battery storage · Flexen USA LLC
514 MWIn study Grimes, TXERCOT Feb 2024target 2028
Midnight Sun Energy Storage
Battery storage · Midnight Sun Energy Storage, LLC
510 MWAgreement signed Crockett, TXERCOT Dec 2022target 2028
Crescent C BESS
Battery storage · OCI La Salle ESS LLC
508 MWIn study La Salle, TXERCOT Apr 2023target 2028
Bayside BESS
Battery storage
508 MWPaused / redesign Victoria, TXERCOT Mar 2022
Point Mountain Storage
Battery storage
507 MWPaused / redesign Upton, TXERCOT
Freedom Falcon BESS
Battery storage · Falcon BESS, LLC
502 MWIn study Zapata, TXERCOT Jun 2023target 2028
Orbit Energy Storage
Battery storage · GCI Orbit Energy Storage, LLC
502 MWIn study Bexar, TXERCOT Nov 2023target 2027
Millsing BESS
Battery storage · Millsing BESS
502 MWIn study Grimes, TXERCOT Feb 2024target 2028
Betel Storage I
Battery storage · BETEL STORAGE I
500 MWIn study Milam, TXERCOT Jan 2025target 2026
Betel Storage II
Battery storage · BETEL STORAGE II
500 MWIn study Milam, TXERCOT Jan 2025target 2026
Gamay Energy Storage
Battery storage · GAMAY ENERGY STORAGE LLC
419 MWAgreement signed Brazoria, TXERCOT Feb 2024target 2027
Bypass BESS II
Battery storage · Bypass BESS II LLC
416 MWIn study Fort Bend, TXERCOT Nov 2024target 2027
BRP Artemis BESS
Battery storage · BRP Artemis BESS LLC
411 MWIn study Grimes, TXERCOT Dec 2021target 2028
BRP Snowdon BESS
Battery storage · BRP SNOWDON BESS LLC
411 MWIn study Briscoe, TXERCOT Sep 2021target 2028
BRP Mekong BESS
Battery storage · BRP Mekong BESS LLC
410 MWIn study Robertson, TXERCOT Dec 2021target 2027
Wilson BESS
Battery storage · Dunamis BESS
410 MWIn study Wilson, TXERCOT Apr 2025target 2028
McCamey's Castle Battery
Battery storage · Castle Storage, LLC
410 MWAgreement signed Upton, TXERCOT Oct 2023target 2027
Beacon Storage
Battery storage · AES Distributed Energy, Inc
409 MWIn study Harris, TXERCOT May 2021target 2029
Sigma Storage
Battery storage · AES Distributed Energy, Inc
408 MWIn study Harris, TXERCOT May 2021target 2029
Lund Storage Center 1
Battery storage · Lund Storage Center 1, LLC
408 MWIn study Bastrop, TXERCOT Jan 2023target 2026
18-Bravo BESS
Battery storage · Scout Energy Management, LLC
407 MWIn study Hunt, TXERCOT Apr 2025target 2028
Claire BESS
Battery storage · BRP Blue Topaz 3, LLC
406 MWIn study Harris, TXERCOT Feb 2023target 2027
Bernice Energy Storage
Battery storage · Bernice Energy Storage LLC
403 MWIn study Bexar, TXERCOT Sep 2024target 2027
Merope BESS
Battery storage · BRP Merope BESS LLC
402 MWIn study Comanche, TXERCOT Dec 2021target 2028
Iron Belt Energy Storage
Battery storage · Iron Belt Energy Storage Project, LLC
402 MWAgreement signed Borden, TXERCOT Jan 2023target 2027
Corruscant BESS
Battery storage · AEU Battery Project III LLC
402 MWIn study Dickens, TXERCOT Feb 2024target 2027
Aldrin 345 BESS
Battery storage · Aldrin Energy Storage LLC
362 MWAgreement signed Brazoria, TXERCOT May 2023target 2027
Wildflower Storage
Battery storage · Wildflower Storage LLC
359 MWIn study Navarro, TXERCOT Jun 2025target 2028
Brookesmith Storage
Battery storage · Brookesmith Storage LLC
351 MWIn study Brown, TXERCOT Apr 2025target 2029
Rabbit Hollow Energy Storage
Battery storage · Rabbit Hollow Energy Storage, LLC
342 MWIn study Mitchell, TXERCOT Dec 2024target 2028
Page 1 of 15

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)