BATTERY STORAGE · ERCOTBetel Storage I
Betel Storage I is a 500 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Milam County, Texas.
Queue statusIn planning
- PlanningQueued Jan 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0630
- Grid region
- ERCOT (Texas)
- Developer
- BETEL STORAGE I
- Connection point (POI)
- 3377 Little Pond Switch ( LTPSW) 345
- Location
- Milam County, Texas
- Technology
- Battery: 500 MW
- Total requested
- 500 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 28 January 2025
- Proposed online date
- August 2026
Location
Marker shows the centre of Milam County; the queue data does not give exact sites.
Other requests in Milam County
- Sypert Branch Solar ProjectSolar · 261 MW · agreement signed
- Eastbell Milam SolarSolar · 245 MW · agreement signed
- Adelite StorageBattery storage · 232 MW · agreement signed
- Hoyte SolarSolar · 207 MW · agreement signed
- Stoneridge SolarSolar · 202 MW · agreement signed
- Yaupon Solar SLFSolar · 201 MW · agreement signed
- Camino Santiago SolarSolar · 196 MW · agreement signed
- Dos Rios Energy Storage SLFBattery storage · 165 MW · agreement signed
- Eastbell Milam Solar IISolar · 151 MW · agreement signed
- Happy Dog StorageSolar + storage · 105 MW · agreement signed
- Stoneridge BESSBattery storage · 102 MW · agreement signed
- HappyDogSolarSolar + storage · 85.5 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem