United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in ERCOT (Texas) (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown172,075 MW
Active in queue104.0 GW361 requests
Agreement signed4,428 MW22 requests
Withdrawn172,075 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

17 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Firefox BESS
Battery storage Β· Horizon Energy Storage Greenfield Project Holdings LLC
258 MWWithdrawn / abandoned ERCOT Mar 2025target 2028
Briggs Storage II
Battery storage Β· Briggs Solar, LLC
250 MWWithdrawn / abandoned Haskell, TXERCOT Jun 2025target 2027
King Cabbage Solar
Solar Β· ACE DevCo NC, LLC
250 MWWithdrawn / abandoned ERCOT Feb 2025target 2028
Iron Wolf Solar
Solar Β· RWE Solar Development, LLC
200 MWWithdrawn / abandoned ERCOT Feb 2025target 2028
Glade Storage
Battery storage Β· Glade Storage, LLC
162 MWWithdrawn / abandoned ERCOT Feb 2025target 2029
Iron Wolf BESS
Battery storage Β· RWE Solar Development, LLC
150 MWWithdrawn / abandoned ERCOT Feb 2025target 2028
Southern Star Solar SLF
Solar Β· Southern Star Solar Project, LLC
116 MWWithdrawn / abandoned ERCOT Mar 2025target 2029
Cycle Storage
Battery storage Β· Grenergy USA
105 MWWithdrawn / abandoned ERCOT Apr 2025target 2028
swoose BESS III
Battery storage Β· Tempus power management LLC
104 MWWithdrawn / abandoned ERCOT Jan 2025target 2026
Highline BESS
Battery storage Β· Highline BESS
103 MWWithdrawn / abandoned ERCOT Feb 2025target 2027
Winslow Storage
Battery storage Β· Winslow Storage, LLC
101 MWWithdrawn / abandoned ERCOT Feb 2025target 2029
Gardner Draw 2 Solar
Solar Β· RWE Solar Development, LLC
100 MWWithdrawn / abandoned ERCOT Sep 2025target 2027
Zircon BESS
Battery storage Β· Zircon BESS LLC
80.4 MWWithdrawn / abandoned La Salle, TXERCOT Jan 2025target 2028
Southern Star Storage SLF
Battery storage Β· Southern Star Solar Project, LLC
51.1 MWWithdrawn / abandoned ERCOT Mar 2025target 2029
Delek Big Spring Solar
Solar Β· TotalEnergies Distributed Generation USA, LLC
21.4 MWWithdrawn / abandoned Howard, TXERCOT Feb 2025target 2027
Delek Big Spring Storage
Battery storage Β· TotalEnergies Distributed Generation USA, LLC
15.3 MWWithdrawn / abandoned Howard, TXERCOT Feb 2025target 2027
Wieland Substation BESS Unit 1
Battery storage Β· Telios Quinlan Energy One, LLC
9.9 MWWithdrawn / abandoned ERCOT Mar 2025target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)