United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Delek Big Spring Solar

Delek Big Spring Solar is a 21.4 MW solar request withdrawn in the ERCOT interconnection queue, in Howard County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2025 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
27INR0357
Grid region
ERCOT (Texas)
Developer
TotalEnergies Distributed Generation USA, LLC
Connection point (POI)
POI: Cosden_8 Bus #1332 138 kV POCC: Bus #1 Transformer #1 12.47 kV
Location
Howard County, Texas
Technology
Solar: 21.4 MW
Total requested
21.4 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
24 February 2025
Proposed online date
June 2027
Withdrawn
July 2025

Location

Marker shows the centre of Howard County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Howard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem