πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

BATTERY STORAGE Β· ERCOT

Iron Wolf BESS

Iron Wolf BESS is a 150 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2025 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
26INR0572
Grid region
ERCOT (Texas)
Developer
RWE Solar Development, LLC
Connection point (POI)
Tap 345 kV 3103 Shambruger Switch - 2485 Poetry Switch
Technology
Battery: 150 MW
Total requested
150 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
18 February 2025
Proposed online date
December 2028

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem