United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2025 requests) — page 9
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project AH1-051, Venango County Solar · Deal Solar LLC |
30.0 MW | Withdrawn / abandoned |
| Winslow Landfill Solar Farm Solar · Winslow LF Solar Farm, LLC |
29.4 MW | Withdrawn / abandoned |
| Solar project AG2-181, Dorchester County Solar · Old Line Energy, LLC |
28.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-578, Wayne County Battery storage · Dragonfly Fields Solar Project, LLC |
28.0 MW | Withdrawn / abandoned |
| Solar project AH1-027, Kent County Solar · Calpine Mid-Atlantic Development, LLC |
25.0 MW | Withdrawn / abandoned |
| Solar project AH1-075, Marion County Solar · Chestnut Solar, LLC |
24.7 MW | Withdrawn / abandoned |
| Solar project GEN-2024-342, Sedgwick County Solar |
22.8 MW | Withdrawn / abandoned |
| Other project Q601, Yuma County Other |
21.6 MW | Withdrawn / abandoned |
| Delek Big Spring Solar Solar · TotalEnergies Distributed Generation USA, LLC |
21.4 MW | Withdrawn / abandoned |
| Solar project AG2-120, Martin County Solar · Wildcat Road Solar, LLC |
21.0 MW | Withdrawn / abandoned |
| East Towanda-South Troy 115 kV II Solar · Franklin Energy, LLC |
20.0 MW | Withdrawn / abandoned |
| McKean Solar 1 - 20 MW Solar · McKean County Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| McKean Solar 1 - Energy Storage Battery storage · McKean County Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Pierce Brook - Lewis Run 230 kV Battery storage · McKean County Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Waterford Solar 1 Solar · PD Solar 11 LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-250, Mercer County Solar · Steamboat Solar LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-533, Warren County Battery storage · AF1327 LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-380, Worcester County Solar · Forest Lane Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Churchill Storage Solutions LLC Battery storage · Churchill Storage Solutions LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project Company RC, Washoe County Solar |
20.0 MW | Withdrawn / abandoned |
| Summersweet Energy Center, LLC Battery storage · Summersweet Energy Center, LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-532, Warren County Battery storage · V20 Mansfield LLC |
20.0 MW | Withdrawn / abandoned |
| Summersweet Energy Center, LLC Battery storage · Summersweet Energy Center, LLC |
20.0 MW | Withdrawn / abandoned |
| McKean Solar 2 - 20 MW Solar · McKean County Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project 756, Elmore County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-249, Mercer County Solar · Steamboat Solar LLC |
20.0 MW | Withdrawn / abandoned |
| Pierce Brook - Lewis Run 230 kV Solar · McKean County Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-221, Bradford County Solar · Franklin Energy, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project G1084, Polk County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-136 Solar · Big Sandy Renewables, LLC |
20.0 MW | Withdrawn / abandoned |
| McKean Solar 2 - Energy Storage Battery storage · McKean County Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-005, Lancaster County Solar · Waller Solar I, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-005, Bradford County Solar · Franklin Energy, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-378, Clark County Solar · TerraForm Twin Creeks Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| South Troy - North Towanda 34.5 kV Solar · Franklin Energy, LLC |
20.0 MW | Withdrawn / abandoned |
| Maysville Solar 2 Solar · PD Solar 11 LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-281, Nelson County Solar · Soltage KY DevCo, LLC |
20.0 MW | Withdrawn / abandoned |
| Noels Creek Solar Solar · Noels Creek Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-035, Washington County Solar · Park Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Pierce Brook-Lewis Run 230kV Battery storage · McKean County Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-535, Warren County Battery storage · Mansfield 3 LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-279, Washington County Solar · Franklin Energy, LLC |
20.0 MW | Withdrawn / abandoned |
| Geothermal project T2-001, Iron County Geothermal |
20.0 MW | Withdrawn / abandoned |
| Summersweet Energy Center, LLC Battery storage · Summersweet Energy Center, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-589, Meigs County Solar · Riverlake Energy, LLC |
20.0 MW | Withdrawn / abandoned |
| Tamarack Solar 1 Solar · PD Solar 11 LLC |
20.0 MW | Withdrawn / abandoned |
| Pierce Brook-Lewis Run 230kV Solar · McKean County Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-534, Warren County Battery storage · Mansfield 3 LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-069, Ashland County Solar · JR ME LLC |
17.0 MW | Withdrawn / abandoned |
| Solar project AH1-070, Ashland County Solar · JR ME LLC |
17.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- SPP (Southwest Power Pool)99 · 26.5 GW
- MISO (Midcontinent)62 · 22.5 GW
- West (non-ISO utilities)75 · 20.5 GW
- PJM (Mid-Atlantic, Midwest)160 · 15.8 GW
- Southeast (non-ISO utilities)44 · 8,611 MW
- ERCOT (Texas)17 · 2,075 MW
- NYISO (New York)16 · 1,089 MW
- ISO-NE (New England)1 · 5.0 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)