Withdrawn queue requests in the USA (2025 requests) — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown47497.1 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

474 requests · page 9 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH1-051, Venango County
Solar · Deal Solar LLC
30.0 MWWithdrawn / abandoned Venango, PAPJM Jan 2025target 2023
Winslow Landfill Solar Farm
Solar · Winslow LF Solar Farm, LLC
29.4 MWWithdrawn / abandoned Camden, NJPJM Mar 2025target 2022
Solar project AG2-181, Dorchester County
Solar · Old Line Energy, LLC
28.0 MWWithdrawn / abandoned Dorchester, MDPJM Mar 2025target 2024
Battery storage project AH1-578, Wayne County
Battery storage · Dragonfly Fields Solar Project, LLC
28.0 MWWithdrawn / abandoned Wayne, OHPJM Feb 2025target 2028
Solar project AH1-027, Kent County
Solar · Calpine Mid-Atlantic Development, LLC
25.0 MWWithdrawn / abandoned Kent, DEPJM Feb 2025target 2023
Solar project AH1-075, Marion County
Solar · Chestnut Solar, LLC
24.7 MWWithdrawn / abandoned Marion, OHPJM Feb 2025target 2022
Solar project GEN-2024-342, Sedgwick County
Solar
22.8 MWWithdrawn / abandoned Sedgwick, KSSPP Mar 2025target 2027
Other project Q601, Yuma County
Other
21.6 MWWithdrawn / abandoned Yuma, AZWest May 2025target 2025
Delek Big Spring Solar
Solar · TotalEnergies Distributed Generation USA, LLC
21.4 MWWithdrawn / abandoned Howard, TXERCOT Feb 2025target 2027
Solar project AG2-120, Martin County
Solar · Wildcat Road Solar, LLC
21.0 MWWithdrawn / abandoned Martin, NCPJM Feb 2025target 2024
East Towanda-South Troy 115 kV II
Solar · Franklin Energy, LLC
20.0 MWWithdrawn / abandoned Bradford, PANYISO Sep 2025
McKean Solar 1 - 20 MW
Solar · McKean County Solar, LLC
20.0 MWWithdrawn / abandoned Mckean, PAPJM Feb 2025target 2024
McKean Solar 1 - Energy Storage
Battery storage · McKean County Solar, LLC
20.0 MWWithdrawn / abandoned Mckean, PAPJM Feb 2025target 2024
Pierce Brook - Lewis Run 230 kV
Battery storage · McKean County Solar, LLC
20.0 MWWithdrawn / abandoned Mckean, PANYISO Sep 2025
Waterford Solar 1
Solar · PD Solar 11 LLC
20.0 MWWithdrawn / abandoned Erie, PAPJM Jan 2025target 2024
Solar project AG2-250, Mercer County
Solar · Steamboat Solar LLC
20.0 MWWithdrawn / abandoned Mercer, PAPJM Mar 2025target 2023
Battery storage project AG2-533, Warren County
Battery storage · AF1327 LLC
20.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2025target 2021
Solar project AH1-380, Worcester County
Solar · Forest Lane Solar, LLC
20.0 MWWithdrawn / abandoned Worcester, MDPJM Feb 2025target 2024
Churchill Storage Solutions LLC
Battery storage · Churchill Storage Solutions LLC
20.0 MWWithdrawn / abandoned City Of Hopewell, VAPJM Feb 2025target 2023
Solar project Company RC, Washoe County
Solar
20.0 MWWithdrawn / abandoned Washoe, NVWest Mar 2025target 2026
Summersweet Energy Center, LLC
Battery storage · Summersweet Energy Center, LLC
20.0 MWWithdrawn / abandoned Fauquier, VAPJM Feb 2025target 2023
Battery storage project AG2-532, Warren County
Battery storage · V20 Mansfield LLC
20.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2025target 2022
Summersweet Energy Center, LLC
Battery storage · Summersweet Energy Center, LLC
20.0 MWWithdrawn / abandoned Fauquier, VAPJM Feb 2025target 2023
McKean Solar 2 - 20 MW
Solar · McKean County Solar, LLC
20.0 MWWithdrawn / abandoned Mckean, PAPJM Feb 2025target 2024
Battery storage project 756, Elmore County
Battery storage
20.0 MWWithdrawn / abandoned Elmore, IDWest Jan 2025
Solar project AG2-249, Mercer County
Solar · Steamboat Solar LLC
20.0 MWWithdrawn / abandoned Mercer, PAPJM Mar 2025target 2023
Pierce Brook - Lewis Run 230 kV
Solar · McKean County Solar, LLC
20.0 MWWithdrawn / abandoned Mckean, PANYISO Sep 2025
Solar project AG2-221, Bradford County
Solar · Franklin Energy, LLC
20.0 MWWithdrawn / abandoned Bradford, PAPJM Jan 2025target 2024
Solar project G1084, Polk County
Solar
20.0 MWWithdrawn / abandoned Polk, ORWest Aug 2025target 2028
Solar project AH1-136
Solar · Big Sandy Renewables, LLC
20.0 MWWithdrawn / abandoned KYPJM Mar 2025target 2024
McKean Solar 2 - Energy Storage
Battery storage · McKean County Solar, LLC
20.0 MWWithdrawn / abandoned Mckean, PAPJM Feb 2025target 2024
Solar project AG2-005, Lancaster County
Solar · Waller Solar I, LLC
20.0 MWWithdrawn / abandoned Lancaster, VAPJM Feb 2025target 2022
Solar project AH1-005, Bradford County
Solar · Franklin Energy, LLC
20.0 MWWithdrawn / abandoned Bradford, PAPJM Jan 2025target 2025
Solar project AG2-378, Clark County
Solar · TerraForm Twin Creeks Solar, LLC
20.0 MWWithdrawn / abandoned Clark, OHPJM Mar 2025target 2023
South Troy - North Towanda 34.5 kV
Solar · Franklin Energy, LLC
20.0 MWWithdrawn / abandoned Bradford, PANYISO Sep 2025
Maysville Solar 2
Solar · PD Solar 11 LLC
20.0 MWWithdrawn / abandoned Mercer, PAPJM Jan 2025target 2024
Solar project AH1-281, Nelson County
Solar · Soltage KY DevCo, LLC
20.0 MWWithdrawn / abandoned Nelson, KYPJM Mar 2025target 2024
Noels Creek Solar
Solar · Noels Creek Solar, LLC
20.0 MWWithdrawn / abandoned Cambria, PAPJM Mar 2025target 2022
Solar project AH1-035, Washington County
Solar · Park Solar, LLC
20.0 MWWithdrawn / abandoned Washington, NCPJM Feb 2025target 2024
Pierce Brook-Lewis Run 230kV
Battery storage · McKean County Solar, LLC
20.0 MWWithdrawn / abandoned Mckean, PANYISO Sep 2025
Battery storage project AG2-535, Warren County
Battery storage · Mansfield 3 LLC
20.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2025target 2022
Solar project AG2-279, Washington County
Solar · Franklin Energy, LLC
20.0 MWWithdrawn / abandoned Washington, MDPJM Feb 2025target 2024
Geothermal project T2-001, Iron County
Geothermal
20.0 MWWithdrawn / abandoned Iron, UTWest Jul 2025target 2026
Summersweet Energy Center, LLC
Battery storage · Summersweet Energy Center, LLC
20.0 MWWithdrawn / abandoned Fauquier, VAPJM Feb 2025target 2023
Solar project AG2-589, Meigs County
Solar · Riverlake Energy, LLC
20.0 MWWithdrawn / abandoned Meigs, OHPJM Mar 2025target 2024
Tamarack Solar 1
Solar · PD Solar 11 LLC
20.0 MWWithdrawn / abandoned Crawford, PAPJM Mar 2025target 2024
Pierce Brook-Lewis Run 230kV
Solar · McKean County Solar, LLC
20.0 MWWithdrawn / abandoned Mckean, PANYISO Sep 2025
Battery storage project AG2-534, Warren County
Battery storage · Mansfield 3 LLC
20.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2025target 2022
Solar project AH1-069, Ashland County
Solar · JR ME LLC
17.0 MWWithdrawn / abandoned Ashland, OHPJM Mar 2025target 2023
Solar project AH1-070, Ashland County
Solar · JR ME LLC
17.0 MWWithdrawn / abandoned Ashland, OHPJM Mar 2025target 2023
Page 9 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)