United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
SOLAR Β· PJMTamarack Solar 1
Tamarack Solar 1 is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Crawford County, Pennsylvania, connecting to PENELEC.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2025 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-490
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PENELEC
- Developer
- PD Solar 11 LLC
- Connection point (POI)
- Venango Junction - Cambridge Springs 34.5 kV
- Location
- Crawford County, Pennsylvania
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 12 March 2025
- Proposed online date
- July 2024
- Withdrawn
- December 2025
Location
Marker shows the centre of Crawford County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Crawford County
- Franklin SolarSolar Β· 20.0 MW Β· agreement signed
- Nichols SolarSolar Β· 20.0 MW Β· agreement signed
- Henry SolarSolar Β· 20.0 MW Β· agreement signed
- Welcome Solar IISolar + storage Β· 19.9 MW Β· agreement signed
- Welcome Solar III, LLCSolar + storage Β· 17.9 MW Β· agreement signed
- Solar project AG2-176, Crawford CountySolar Β· 150 MW Β· in study
- Battery storage project AH2-420, Crawford CountyBattery storage Β· 50.0 MW Β· in study
- Solar project AH2-119, Crawford CountySolar Β· 15.0 MW Β· in study
- Solar project AH2-095, Crawford CountySolar Β· 3.3 MW Β· in study
- Solar project AI1-160, Crawford CountySolar Β· 1.4 MW Β· in study
- Shorebird SolarSolar Β· 117 MW Β· suspended
- Morgan Street-Cochranton 34.5 kVSolar Β· 15.0 MW Β· suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem