United States βΊ Grid βΊ Interconnection queues βΊ Kansas
SOLAR Β· SPPSolar project GEN-2024-342, Sedgwick County
Solar project GEN-2024-342, Sedgwick County is a 22.8 MW solar request withdrawn in the SPP interconnection queue, in Sedgwick County, Kansas, connecting to Evergy.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2025 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2024-342
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- Evergy
- Connection point (POI)
- Tap on Chisholm - Grant Junction 69 kV Line
- Location
- Sedgwick County, Kansas
- Technology
- Solar: 22.8 MW
- Total requested
- 22.8 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 1 March 2025
- Proposed online date
- July 2027
- Withdrawn
- July 2025
Location
Marker shows the centre of Sedgwick County; the queue data does not give exact sites.
Other requests in Sedgwick County
- Solar project GEN-2018-057, Sedgwick CountySolar Β· 203 MW Β· agreement signed
- Solar project GEN-2017-226, Sedgwick CountySolar Β· 202 MW Β· agreement signed
- Battery storage project GEN-2017-227, Sedgwick CountyBattery storage Β· 202 MW Β· agreement signed
- Solar project GEN-2017-220, Sedgwick CountySolar Β· 202 MW Β· agreement signed
- Battery storage project GEN-2017-221, Sedgwick CountyBattery storage Β· 152 MW Β· agreement signed
- Solar + storage project GEN-2024-166, Sedgwick CountySolar + storage Β· 275 MW Β· in study
- Solar project GEN-2023-034, Sedgwick CountySolar Β· 130 MW Β· in study
- Solar project GEN-2022-004, Sedgwick CountySolar Β· 33.0 MW Β· in study
- Gas project GEN-2006-029, Sedgwick CountyGas Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2017-179, Sedgwick CountyOnshore wind Β· 222 MW Β· withdrawn
- Solar + storage project GEN-2023-186, Sedgwick CountySolar + storage Β· 200 MW Β· withdrawn
- Solar project GEN-2021-061, Sedgwick CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem