United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Waterford Solar 1

Waterford Solar 1 is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Erie County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-491
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Developer
PD Solar 11 LLC
Connection point (POI)
Union City 34.5 kV
Location
Erie County, Pennsylvania
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 January 2025
Proposed online date
July 2024
Withdrawn
December 2025

Location

Marker shows the centre of Erie County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Erie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem