| Project | Capacity | Status |
|---|---|---|
| Topaz Storage Project Battery storage · Hanwha Q CELLS USA |
200 MW | Withdrawn / abandoned |
| Egc BESS II Battery storage · Jupiter Power LLC |
200 MW | Withdrawn / abandoned |
| QMB2 Energy Storage, LLC Battery storage · QMB2 Energy Storage, LLC |
200 MW | Withdrawn / abandoned |
| Harvest Hills Solar Solar · ConnectGen Cayuga County LLC |
200 MW | Withdrawn / abandoned |
| Riptide Storage Battery storage · ACE DevCo NC,LLC |
200 MW | Withdrawn / abandoned |
| Sweet Valley Storage Battery storage · Sweet Valley Energy Center |
200 MW | Withdrawn / abandoned |
| Sapphire Solar and Storage Solar + storage · Hanwha Q CELLS USA |
200 MW | Withdrawn / abandoned |
| EI Steinway 1.1 Offshore wind · Beacon Wind LLC |
200 MW | Withdrawn / abandoned |
| Southern Tier Energy Center Battery storage · Southern Tier Energy Center, LLC |
200 MW | Withdrawn / abandoned |
| Sullivan County Solar & BESS Solar + storage · RWE Solar Development |
200 MW | Withdrawn / abandoned |
| Mossy Bank Solar Solar · ACE DevCo NC, LLC |
200 MW | Withdrawn / abandoned |
| Flat Creek Solar Solar · Flat Creek Solar NY LLC |
200 MW | Withdrawn / abandoned |
| BPP NY Lansing BESS I Battery storage · Bear Peak Power LLC |
200 MW | Withdrawn / abandoned |
| Harvest Hills Solar Solar + storage · ConnectGen Cayuga County LLC |
200 MW | Withdrawn / abandoned |
| Ditch Creek Solar Solar + storage · Nexamp Solar LLC |
200 MW | Withdrawn / abandoned |
| Independence BESS Battery storage · Independence BESS LLC |
200 MW | Withdrawn / abandoned |
| Nine Mile Wind Energy Onshore wind · Terra-Gen Development Company, LLC |
200 MW | Withdrawn / abandoned |
| Ditch Creek Solar + storage · Ditch Creek Solar LLC |
200 MW | Withdrawn / abandoned |
| BPP NY Somerset BESS I LLC Battery storage · BPP NY Somerset BESS I LLC |
200 MW | Withdrawn / abandoned |
| North Creek Solar + storage · North Creek Solar LLC |
200 MW | Withdrawn / abandoned |
| Machias II Onshore wind · Machias Wind Farm, LLC |
200 MW | Withdrawn / abandoned |
| ELP Clay Storage Battery storage · ELP Clay Storage LLC |
199 MW | Withdrawn / abandoned |
| Verona Solar I Solar · Verona Solar |
199 MW | Withdrawn / abandoned |
| Summersweet Energy Center Battery storage · Summersweet Energy Center, LLC |
199 MW | Withdrawn / abandoned |
| Honey Bee Battery Storage, LLC Battery storage · BayWa r.e Projects LLC. |
199 MW | Withdrawn / abandoned |
| Beacon Harbor Solar Solar + storage · Beacon Harbor Solar Project, LLC |
195 MW | Withdrawn / abandoned |
| Marcy BESS 2 Battery storage · The Commodore Storage, LLC |
195 MW | Withdrawn / abandoned |
| Clover Leaf Hollers Ave Gas · Clover Leaf Power, LLC |
193 MW | Withdrawn / abandoned |
| Celestine Storage Battery storage · Hanwha Q CELLS USA |
191 MW | Withdrawn / abandoned |
| Gemma Storage Battery storage · Hanwha Q CELLS USA |
190 MW | Withdrawn / abandoned |
| Capital Energy Storage Battery storage · BGTF US Development Holdings LLC |
190 MW | Withdrawn / abandoned |
| Ravenswood Energy Storage Battery storage · Ravenswood Development, LLC |
187 MW | Withdrawn / abandoned |
| Lockport Storage Battery storage · Origis Development |
186 MW | Withdrawn / abandoned |
| Taproot Solar Solar · Taproot Solar LLC |
185 MW | Withdrawn / abandoned |
| Bath Solar Solar + storage · Bath Solar LLC |
185 MW | Withdrawn / abandoned |
| NY New Scotland 99 New Scotland South Rd Storage Battery storage · Bluewave Origination LLC |
181 MW | Withdrawn / abandoned |
| Sugarloaf BESS Battery storage · Empire Reserve Energy, LLC |
180 MW | Withdrawn / abandoned |
| Niagara Dolomite Solar Solar · Niagara Dolomite Solar, LLC |
180 MW | Withdrawn / abandoned |
| Elevate Arthur Kill II, LLC Battery storage · Elevate Arthur Kill, LLC |
180 MW | Withdrawn / abandoned |
| Lovett #3 Repowering Other · Mirant |
180 MW | Withdrawn / abandoned |
| South Dow (Lucy's Energy Reserve) Battery storage · Lucy?s Energy Reserve LLC |
175 MW | Withdrawn / abandoned |
| Armenia Mountain I Onshore wind · AES Keystone Wind, LLC |
175 MW | Withdrawn / abandoned |
| Erie-Wyoming County Solar Solar + storage · ConnectGen Erie-Wyoming LLC |
175 MW | Withdrawn / abandoned |
| Crystal Storage Project Battery storage · Hanwha Q CELLS USA |
175 MW | Withdrawn / abandoned |
| Emerald Solar and Storage Solar · Hanwha Q CELLS USA |
174 MW | Withdrawn / abandoned |
| Garnet Solar and Storage Solar · Hanwha Q CELLS USA |
174 MW | Withdrawn / abandoned |
| Astoria Repowering-Phase 2 Gas · Reliant Energy |
173 MW | Withdrawn / abandoned |
| Lewis Run - Pierce Brook 230 kV Battery storage · RWE Solar Development, LLC |
170 MW | Withdrawn / abandoned |
| Basecamp BESS Battery storage · RWE Solar Development |
170 MW | Withdrawn / abandoned |
| McKean County BESS Battery storage · RWE Solar Development, LLC |
170 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)