πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

ONSHORE WIND Β· NYISO

Machias II

Machias II is a 200 MW onshore wind request withdrawn in the NYISO interconnection queue, in Cattaraugus County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2008 (completed)
  2. Withdrawn / abandonedApr 2009 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
286
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Machias Wind Farm, LLC
Connection point (POI)
345kV
Location
Cattaraugus County, New York
Technology
Wind: 200 MW
Total requested
200 MW
Queue status
Withdrawn
Entered queue
27 March 2008
Withdrawn
April 2009

Location

Marker shows the centre of Cattaraugus County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Cattaraugus County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem