BATTERY STORAGE · NYISO

Celestine Storage

Celestine Storage is a 191 MW battery storage request withdrawn in the NYISO interconnection queue, in Steuben County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedJun 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1347
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Hanwha Q CELLS USA
Connection point (POI)
Bath 115 kV substation
Location
Steuben County, New York
Technology
Battery: 191 MW
Total requested
191 MW
Queue status
Withdrawn
Entered queue
11 March 2022
Withdrawn
June 2022

Location

Marker shows the centre of Steuben County; the queue data does not give exact sites.