BATTERY STORAGE Β· NYISOSugarloaf BESS
Sugarloaf BESS is a 180 MW battery storage request withdrawn in the NYISO interconnection queue, in Orange County, New York, connecting to O&R.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1573
- Grid region
- NYISO (New York)
- Utility / transmission owner
- O&R
- Developer
- Empire Reserve Energy, LLC
- Connection point (POI)
- 138kV Sugarloaf Substation
- Location
- Orange County, New York
- Technology
- Battery: 180 MW
- Total requested
- 180 MW
- Queue status
- Withdrawn
- Entered queue
- 23 June 2023
Location
Marker shows the centre of Orange County; the queue data does not give exact sites.
Other requests in Orange County
- Sugar Loaf Energy Storage IBattery storage Β· 300 MW Β· in study
- Arch 4Battery storage Β· 150 MW Β· in study
- Farmhouse BESSBattery storage Β· 150 MW Β· in study
- Arch 3Battery storage Β· 100 MW Β· in study
- Little Pond SolarSolar Β· 20.0 MW Β· in study
- CPV Valley Energy CenterGas Β· 691 MW Β· built
- CPV Valley Energy CenterGas Β· 691 MW Β· built
- Swinging Bridge Unit 3Hydro Β· 1.2 MW Β· built
- Swinging Bridge Unit 3Hydro Β· 1.2 MW Β· built
- CPV Valley IIGas Β· 820 MW Β· withdrawn
- Wawayanda Energy CenterGas Β· 500 MW Β· withdrawn
- Sugar Loaf Energy Storage IIBattery storage Β· 300 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem