United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR + STORAGE Β· NYISODitch Creek
Ditch Creek is a 200 MW solar + storage request withdrawn in the NYISO interconnection queue, in Madison County, New York, connecting to NYPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C24-319
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYPA
- Developer
- Ditch Creek Solar LLC
- Connection point (POI)
- CLAY to EDIC 345 kV Line #15 Circuit #2
- Location
- Madison County, New York
- Technology
- Solar: 200 MW Β· Battery
- Total requested
- 200 MW
- Queue status
- Withdrawn
- Entered queue
- 5 October 2024
Location
Marker shows the centre of Madison County; the queue data does not give exact sites.
Other requests in Madison County
- Oxbow Hill SolarSolar Β· 140 MW Β· in study
- Hoffman Falls WindOnshore wind Β· 72.0 MW Β· in study
- Hoffman Falls Wind 2Onshore wind Β· 29.8 MW Β· in study
- Munnsville - Phase 1Onshore wind Β· 34.5 MW Β· built
- Fenner Wind Energy Fac.Onshore wind Β· 30.0 MW Β· built
- Fenner Wind Energy Fac.Onshore wind Β· 30.0 MW Β· built
- Ditch Creek SolarSolar + storage Β· 200 MW Β· withdrawn
- Hoffman Falls Wind 2Onshore wind Β· 103 MW Β· withdrawn
- Cazenovia SolarSolar Β· 80.0 MW Β· withdrawn
- Rolling Upland Wind FarmOnshore wind Β· 79.8 MW Β· withdrawn
- Rolling Upland Wind Farm LLCOnshore wind Β· 79.8 MW Β· withdrawn
- Stockbridge WindOnshore wind Β· 72.6 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem