ONSHORE WIND · NYISO

Rolling Upland Wind Farm LLC

Rolling Upland Wind Farm LLC is a 79.8 MW onshore wind request withdrawn in the NYISO interconnection queue, in Madison County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1549
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Rolling Upland Wind Farm LLC
Connection point (POI)
County-Brothertown Line 115kV
Location
Madison County, New York
Technology
Wind: 79.8 MW
Total requested
79.8 MW
Queue status
Withdrawn
Entered queue
25 April 2023

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Madison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem