United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA — page 80

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 80 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-088, Greene County
Gas
145 MWIn study Greene, MOSPP Oct 2024target 2027
Solar project 962925, Lee County
Solar
145 MWIn study Lee, SCSoutheast Sep 2024
Battery storage project C2-79, Linn County
Battery storage · Creekside Storage LLC
145 MWPaused / redesign Linn, ORWest May 2022target 2025
Solar project J2165, Liberty County
Solar
145 MWIn study Liberty, TXMISO Nov 2021target 2027
Wang Solar SLF
Solar + storage · BT Yixin Solar, LLC
145 MWIn study Falls, TXERCOT Jun 2018target 2026
Solar project J2249, Acadia Parish County
Solar
144 MWIn study Acadia Parish, LAMISO Dec 2021target 2027
Starling Solar
Solar + storage · Starling Solar, LLC
144 MWIn study Gonzales, TXERCOT Oct 2022target 2028
Kankakee Solar
Solar · AEUG Kankakee Solar, LLC
144 MWIn study Kankakee, ILPJM Feb 2020target 2021
Rio Star Energy Storage
Battery storage · Rio Star Energy Storage, LLC
144 MWIn study Wichita, TXERCOT Feb 2025target 2028
Summerhill BESS
Battery storage · Taylor ESS, LLC
143 MWIn study Taylor, TXERCOT Feb 2025target 2028
SR Norwood II
Solar
143 MWIn study Warren, GASoutheast Dec 2024target 2028
Solar project 25-011625, Weld County
Solar
143 MWIn study Weld, COWest Jan 2025target 2026
Battery storage project J3063, Perry County
Battery storage
143 MWIn study Perry, ILMISO Sep 2022target 2026
CH Solterra LLC
Solar · CH Solterra LLC
143 MWIn study Hopkins, TXERCOT Mar 2021target 2026
Gibson Branch BESS
Battery storage · Gibson Branch BESS LLC
143 MWIn study Lampasas, TXERCOT May 2024target 2028
Cherry Sage Solar 1 SLF
Solar + storage · Cherry Sage Solar 1 LLC
143 MWIn study Concho, TXERCOT Apr 2025target 2029
Other project J3400, Deuel County
Other
142 MWIn study Deuel, SDMISO Mar 2024target 2028
Solar project GEN-2024-376, Sabine County
Solar
142 MWIn study Sabine, TXSPP Mar 2025target 2028
Solar project AI2-037, King And Queen County
Solar
142 MWIn study King And Queen, VAPJM Jan 2023target 2027
Solar project AH2-349, Halifax County
Solar
142 MWIn study Halifax, VAPJM Mar 2022target 2025
Solar + storage project J3004, Mason County
Solar + storage
142 MWIn study Mason, ILMISO Sep 2022target 2025
Rhoda Storage
Battery storage · Milam Energy, LLC
141 MWIn study Milam, TXERCOT Apr 2022target 2028
Solar project J3797, Edgar County
Solar
141 MWIn study Edgar, ILMISO Apr 2024target 2028
Spain Energy Center
Solar + storage
141 MWIn study Brooks, GASoutheast Jan 2024target 2028
Invictus Energy Storage
Battery storage · GSA Land Holdings
141 MWIn study Coleman, TXERCOT Jan 2024target 2028
Ramadi Utility Storage
Battery storage · Ramadi LLC
140 MWIn study Suffolk, NYNYISO Sep 2024target 2028
Battery storage project ERAS-2025-036, Potter County
Battery storage
140 MWIn study Potter, TXSPP Oct 2025target 2029
Solar project AH1-188, Mingo County
Solar · Twisted Gun Solar, LLC
140 MWIn study Mingo, WVPJM Feb 2025target 2025
Solar project AG2-442, Charlotte County
Solar · Taro Solar LLC
140 MWIn study Charlotte, VAPJM Apr 2025target 2024
Wind + storage project 347, Wheatland County
Wind + storage
140 MWPaused / redesign Wheatland, MTWest Jul 2018target 2024
Solar + storage project 25RSC-010, Graves County
Solar + storage
140 MWIn study Graves, KYSoutheast Aug 2025target 2031
Solar + storage project GEN-2024-362, Grady County
Solar + storage
140 MWIn study Grady, OKSPP Mar 2025target 2029
Solar project J4188, Beauregard Parish County
Solar
140 MWIn study Beauregard Parish, LAMISO Oct 2025target 2029
Greens Bayou Expansion
Gas
140 MWPaused / redesign Harris, TXERCOT Apr 2019
Solar + storage project J3229, Maries County
Solar + storage
140 MWIn study Maries, MOMISO Sep 2022target 2026
Solar project J2901, Columbia County
Solar
140 MWIn study Columbia, ARMISO Sep 2022target 2027
Solar project J2669, Mason County
Solar
140 MWIn study Mason, MIMISO Sep 2022target 2025
Solar project J3611, Hamilton County
Solar
140 MWIn study Hamilton, ILMISO Apr 2024target 2026
Solar project J2815, Calhoun County
Solar
140 MWIn study Calhoun, MIMISO Aug 2022target 2026
Solar + storage project J2619, Montcalm County
Solar + storage
140 MWIn study Montcalm, MIMISO Sep 2022target 2026
Solar project GEN-2024-157, Kiowa County
Solar
140 MWIn study Kiowa, OKSPP Mar 2025target 2029
Solar + storage project J2593, Gasconade County
Solar + storage
140 MWIn study Gasconade, MOMISO Sep 2022target 2026
Solar project GI-DISIS-2021-06, Montezuma County
Solar
140 MWPaused / redesign Montezuma, COWest May 2021target 2025
Solar project GI-TC-2024-22, Weld County
Solar
140 MWIn study Weld, COWest May 2024target 2028
Solar + storage project Company PO, Eureka County
Solar + storage
140 MWIn study Eureka, NVWest Mar 2023target 2025
Solar project J3233, Yellow Medicine County
Solar
140 MWIn study Yellow Medicine, MNMISO Mar 2024target 2028
Oxbow Hill Solar
Solar · Oxbow Hill Solar, LLC
140 MWIn study Madison, NYNYISO Mar 2019target 2026
Palladium Storage
Battery storage · Palladium Storage LLC
140 MWIn study Bronx, NYNYISO Aug 2024target 2028
Solar project J3913, Amite County
Solar
140 MWIn study Amite, MSMISO Oct 2024target 2030
Solar project J2812, Hillsdale County
Solar
140 MWIn study Hillsdale, MIMISO Sep 2022target 2026
Page 80 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)