🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › South Carolina

SOLAR · SOUTHEAST

Solar project 962925, Lee County

Solar project 962925, Lee County is a 145 MW solar request in interconnection study in the Southeast interconnection queue, in Lee County, South Carolina, connecting to Duke Energy Progress.

Queue statusIn planning
  1. PlanningQueued Sep 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
962925
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Connection point (POI)
Robinson Plant - Sumter 230kV
Location
Lee County, South Carolina
Technology
Solar: 145 MW
Total requested
145 MW
Service type
Network resource (NRIS)
Study phase
Phase 2 Cluster Study - In Progress
Queue status
Active
Entered queue
26 September 2024

Location

Marker shows the centre of Lee County; the queue data does not give exact sites.

Power plants in South Carolina · Transmission lines in South Carolina

Other requests in Lee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem