United States › Grid › Interconnection queues › South Carolina
SOLAR · SOUTHEASTSolar project 962925, Lee County
Solar project 962925, Lee County is a 145 MW solar request in interconnection study in the Southeast interconnection queue, in Lee County, South Carolina, connecting to Duke Energy Progress.
- PlanningQueued Sep 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 962925
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Progress
- Connection point (POI)
- Robinson Plant - Sumter 230kV
- Location
- Lee County, South Carolina
- Technology
- Solar: 145 MW
- Total requested
- 145 MW
- Service type
- Network resource (NRIS)
- Study phase
- Phase 2 Cluster Study - In Progress
- Queue status
- Active
- Entered queue
- 26 September 2024
Location
Marker shows the centre of Lee County; the queue data does not give exact sites.
Power plants in South Carolina · Transmission lines in South Carolina
Other requests in Lee County
- Solar project 566580, Lee CountySolar · 60.0 MW · under construction
- Solar project PP00010, Lee CountySolar · 60.0 MW · under construction
- Other project PP00034, Lee CountyOther · 145 MW · in study
- Solar project 8277, Lee CountySolar · 100 MW · withdrawn
- Solar project 17236, Lee CountySolar · 75.0 MW · withdrawn
- Solar project 569814, Lee CountySolar · 74.9 MW · withdrawn
- Solar project 962757, Lee CountySolar · 70.0 MW · withdrawn
- Solar project 25592, Lee CountySolar · 2.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem