🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › South Carolina

SOLAR · SOUTHEAST

Solar project PP00010, Lee County

Solar project PP00010, Lee County is a 60.0 MW solar request under construction in the Southeast interconnection queue, in Lee County, South Carolina, connecting to Duke Energy Progress.

Queue statusUnder construction
  1. PlanningQueued Jan 2025 (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
PP00010
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Connection point (POI)
ROBINSON PLANT - SUMTER
Location
Lee County, South Carolina
Technology
Solar: 60.0 MW
Total requested
60.0 MW
Study phase
Provisional Construction in Progress
Queue status
Active
Entered queue
13 January 2025
Proposed online date
December 2028

Location

Marker shows the centre of Lee County; the queue data does not give exact sites.

Power plants in South Carolina · Transmission lines in South Carolina

Other requests in Lee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem