United States βΊ Grid βΊ Interconnection queues βΊ South Carolina
SOLAR Β· SOUTHEASTSolar project 25592, Lee County
Solar project 25592, Lee County is a 2.0 MW solar request withdrawn in the Southeast interconnection queue, in Lee County, South Carolina, connecting to Duke Energy Progress.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2019 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 25592
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Progress
- Connection point (POI)
- ELLIOTT 230KV
- Location
- Lee County, South Carolina
- Technology
- Solar: 2.0 MW
- Total requested
- 2.0 MW
- Service type
- Other
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 17 January 2019
Location
Marker shows the centre of Lee County; the queue data does not give exact sites.
Power plants in South Carolina Β· Transmission lines in South Carolina
Other requests in Lee County
- Solar project 566580, Lee CountySolar Β· 60.0 MW Β· under construction
- Solar project PP00010, Lee CountySolar Β· 60.0 MW Β· under construction
- Other project PP00034, Lee CountyOther Β· 145 MW Β· in study
- Solar project 962925, Lee CountySolar Β· 145 MW Β· in study
- Solar project 8277, Lee CountySolar Β· 100 MW Β· withdrawn
- Solar project 17236, Lee CountySolar Β· 75.0 MW Β· withdrawn
- Solar project 569814, Lee CountySolar Β· 74.9 MW Β· withdrawn
- Solar project 962757, Lee CountySolar Β· 70.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem